Credible Regulation-Capability Assessment for Industrial-Park Virtual Power Plants Considering Source–Load Uncertainty

Industrial-park virtual power plants (VPPs) must provide regulation despite forecast errors in industrial demand and photovoltaic (PV) generation and the recovery requirements of flexible resources. This paper develops a day-ahead capability assessment framework for a single 2.5 h regulation activation. Each scenario-specific capability value is obtained from a feasible full-day schedule for aggregate production loads, auxiliary systems, and energy storage, including post-activation recovery. Causal load–PV forecast-error trajectories are organized into macro-operating regimes and representative sub-scenarios, while a conditional value-at-risk (CVaR) constraint enforces a risk budget for the worst-start reserve shortfall under the reduced 12-medoid scenario distribution. The framework is evaluated against the complete historical error distribution and over 300 chronological operating days. Compared with scenario expectation, the proposed method reduces mean downward worst-event shortfall (12.565 versus 14.062 kWh). The single-forecast benchmark nevertheless achieves slightly lower upward estimation error and worst-event shortfall and a higher mean illustrative net benefit. Across 12 chronological risk-audit dates, the full-history CVaR exceeds the reduced-scenario estimate in both directions, with the calibrated risk budgets exceeded on all 12 upward dates and four downward dates under the full historical distribution. Thus, the proposed framework provides a recovery-aware, scenario-conditional risk-budgeted approach to reserve declaration, clarifying the trade-offs among deliverability, tail risk, estimation accuracy, and economic return. Ex-post reference capabilities are reconstructed from hourly measurements.

Authors

Institutions

Publication Details

Journal
Electronics
Published
2026-11-27
DOI
https://doi.org/10.3390/electronics15235566
Primary Topic
Electric Power System Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Credible Regulation-Capability Assessment for Industrial-Park Virtual Power Plants Considering Source–Load Uncertainty

Ye Dong, Fei Wang, Xiaoke Li, Yunze Li et al.
Electronics
Electric Power System Optimization
article

Credible Regulation-Capability Assessment for Industrial-Park Virtual Power Plants Considering Source–Load Uncertainty

Ye Dong, Fei Wang, Xiaoke Li, Yunze Li, Aoqian Wang, Tao Zhang
article en

Abstract

Industrial-park virtual power plants (VPPs) must provide regulation despite forecast errors in industrial demand and photovoltaic (PV) generation and the recovery requirements of flexible resources. This paper develops a day-ahead capability assessment framework for a single 2.5 h regulation activation. Each scenario-specific capability value is obtained from a feasible full-day schedule for aggregate production loads, auxiliary systems, and energy storage, including post-activation recovery. Causal load–PV forecast-error trajectories are organized into macro-operating regimes and representative sub-scenarios, while a conditional value-at-risk (CVaR) constraint enforces a risk budget for the worst-start reserve shortfall under the reduced 12-medoid scenario distribution. The framework is evaluated against the complete historical error distribution and over 300 chronological operating days. Compared with scenario expectation, the proposed method reduces mean downward worst-event shortfall (12.565 versus 14.062 kWh). The single-forecast benchmark nevertheless achieves slightly lower upward estimation error and worst-event shortfall and a higher mean illustrative net benefit. Across 12 chronological risk-audit dates, the full-history CVaR exceeds the reduced-scenario estimate in both directions, with the calibrated risk budgets exceeded on all 12 upward dates and four downward dates under the full historical distribution. Thus, the proposed framework provides a recovery-aware, scenario-conditional risk-budgeted approach to reserve declaration, clarifying the trade-offs among deliverability, tail risk, estimation accuracy, and economic return. Ex-post reference capabilities are reconstructed from hourly measurements.

ElectronicsVol. 15(23)
North China Electric Power University (CN), State Grid Corporation of China (China) (CN)
Electric Power System Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon
Credible Regulation-Capability Assessment for Industrial-Park Virtual Power Plants Considering Source–Load Uncertainty — Ye Dong, Fei Wang, et al. · Electronics (2026) | TGRS Research Map | TGRS