Analysis of Standard Times and Operator Requirements for the Sewing of IS 1200-900 Type FIBCs Using Time Study and Workload Analysis

This study was conducted on the sewing process of IS 1200-900 type Flexible Intermediate Bulk Containers (FIBCs) on Line 8 at PT X. During observations in July–August 2026, six operators produced 85 units per shift out of a target of 86 units. This study aims to determine standard times and standard rates, assess line capacity and each operator’s workload, calculate the minimum number of operators required, and propose a task allocation plan. The processing time for 12 elements was measured with a stopwatch 30 times per element. Standard time was calculated with a 15% allowance and used in the Workload Analysis (WLA) to compare scenarios with six, seven, and eight operators. Normal time and standard time were 29.25 and 34.41 minutes per unit, respectively. The theoretical capacity for six operators is 86.15 units per shift based on standard time and 73.23 units per shift based on standard time. Actual production closely matches the estimate based on standard time. In this scenario, the target requires 99.83% of working time before the allowance is factored in. At the production target, the total workload reached 49.33 operator-hours per shift, while the available time was only 42 hours. The line’s WLA reached 117.45%, with individual workloads ranging from 53.8% to 180.0%. Four operators were estimated to be overloaded. The seven-operator scenario still yields a line WLA of 100.67%, making eight operators the minimum requirement based on standard time, with an estimated line WLA of 88.08%. The proposed workload balancing divides the work volume among elements A6, A7, and A12 so that each operator’s workload aligns with the available working time. In practice, the research results provide a basis for PT X to determine the number of operators per shift and to develop a task allocation plan before testing the design under actual production conditions.

Authors

Institutions

Publication Details

Journal
Jurnal Riset Ilmu Teknik
Published
2026-11-27
DOI
https://doi.org/10.59976/jurit.v4i3.459
Primary Topic
Assembly Line Balancing Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Analysis of Standard Times and Operator Requirements for the Sewing of IS 1200-900 Type FIBCs Using Time Study and Workload Analysis

Moh. Jufriyanto, Nabiilah Nur Khoiriyyah
Jurnal Riset Ilmu Teknik
Assembly Line Balancing Optimization
article

Analysis of Standard Times and Operator Requirements for the Sewing of IS 1200-900 Type FIBCs Using Time Study and Workload Analysis

Moh. Jufriyanto, Nabiilah Nur Khoiriyyah
article en

Abstract

This study was conducted on the sewing process of IS 1200-900 type Flexible Intermediate Bulk Containers (FIBCs) on Line 8 at PT X. During observations in July–August 2026, six operators produced 85 units per shift out of a target of 86 units. This study aims to determine standard times and standard rates, assess line capacity and each operator’s workload, calculate the minimum number of operators required, and propose a task allocation plan. The processing time for 12 elements was measured with a stopwatch 30 times per element. Standard time was calculated with a 15% allowance and used in the Workload Analysis (WLA) to compare scenarios with six, seven, and eight operators. Normal time and standard time were 29.25 and 34.41 minutes per unit, respectively. The theoretical capacity for six operators is 86.15 units per shift based on standard time and 73.23 units per shift based on standard time. Actual production closely matches the estimate based on standard time. In this scenario, the target requires 99.83% of working time before the allowance is factored in. At the production target, the total workload reached 49.33 operator-hours per shift, while the available time was only 42 hours. The line’s WLA reached 117.45%, with individual workloads ranging from 53.8% to 180.0%. Four operators were estimated to be overloaded. The seven-operator scenario still yields a line WLA of 100.67%, making eight operators the minimum requirement based on standard time, with an estimated line WLA of 88.08%. The proposed workload balancing divides the work volume among elements A6, A7, and A12 so that each operator’s workload aligns with the available working time. In practice, the research results provide a basis for PT X to determine the number of operators per shift and to develop a task allocation plan before testing the design under actual production conditions.

Jurnal Riset Ilmu TeknikVol. 4(3)
Universitas Muhammadiyah Gresik (ID)
Assembly Line Balancing Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon
Analysis of Standard Times and Operator Requirements for the Sewing of IS 1200-900 Type FIBCs Using Time Study and Workload Analysis — Moh. Jufriyanto, Nabiilah Nur Khoiriyyah · Jurnal Riset Ilmu Teknik (2026) | TGRS Research Map | TGRS