Long-term capacity planning of a campus microgrid with flexible pumping demand and outage-aware rule-based energy management

Campus microgrid investments must account for demand growth, flexible loads, and grid outages over the project lifetime. This study develops a 20-year hourly planning framework to select photovoltaic (PV), battery energy storage system (BESS), and diesel capacities together with water-pumping schedules at the University of Gonabad, Iran. A rule-based energy-management system (EMS) evaluates cost, operational CO₂ emissions, and reliability, including throughput-based battery replacement. A multi-objective hybrid particle swarm–grey wolf optimizer (MO-HPSO-GWO) and a weighted-sum particle swarm optimization (PSO) benchmark generate candidate designs, which are pooled to select preference-based compromises. Under a 1% maximum annual loss-of-power-supply probability (LPSP) constraint, the selected hybrid comprises 724.90 kW PV, 50 kW diesel, and 1150 kWh BESS, with pumping shifted by three hours. Its net present cost (NPC) is USD 1.1101 million, 8.09% lower than the feasible PV–diesel–grid alternative, while emissions are 1.84% higher. The grid-only reference exceeds the LPSP limit. Across 100 independently sampled 20-year projects with two-hour outages, both selected grid-connected designs meet the annual limit, but only the PV–diesel–grid design avoids critical-load shortfalls in all projects. Fixed-design replays using 15 historical non-leap solar years also remain below the limit. For fixed hybrid capacities, an annual perfect-foresight mixed-integer linear programming (MILP) benchmark reduces NPC by 7.51% under baseline replacement accounting. The selected designs reveal a trade-off between cost and critical-load service. Planning decisions should therefore consider critical-load interruptions alongside annual LPSP.

Authors

Institutions

Publication Details

Journal
Next Energy
Published
2026-11-27
DOI
https://doi.org/10.1016/j.nxener.2026.101224
Primary Topic
Microgrid Control and Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Long-term capacity planning of a campus microgrid with flexible pumping demand and outage-aware rule-based energy management

Amin Ranjbaran
Next Energy
Microgrid Control and Optimization
article

Long-term capacity planning of a campus microgrid with flexible pumping demand and outage-aware rule-based energy management

Amin Ranjbaran
article en

Abstract

Campus microgrid investments must account for demand growth, flexible loads, and grid outages over the project lifetime. This study develops a 20-year hourly planning framework to select photovoltaic (PV), battery energy storage system (BESS), and diesel capacities together with water-pumping schedules at the University of Gonabad, Iran. A rule-based energy-management system (EMS) evaluates cost, operational CO₂ emissions, and reliability, including throughput-based battery replacement. A multi-objective hybrid particle swarm–grey wolf optimizer (MO-HPSO-GWO) and a weighted-sum particle swarm optimization (PSO) benchmark generate candidate designs, which are pooled to select preference-based compromises. Under a 1% maximum annual loss-of-power-supply probability (LPSP) constraint, the selected hybrid comprises 724.90 kW PV, 50 kW diesel, and 1150 kWh BESS, with pumping shifted by three hours. Its net present cost (NPC) is USD 1.1101 million, 8.09% lower than the feasible PV–diesel–grid alternative, while emissions are 1.84% higher. The grid-only reference exceeds the LPSP limit. Across 100 independently sampled 20-year projects with two-hour outages, both selected grid-connected designs meet the annual limit, but only the PV–diesel–grid design avoids critical-load shortfalls in all projects. Fixed-design replays using 15 historical non-leap solar years also remain below the limit. For fixed hybrid capacities, an annual perfect-foresight mixed-integer linear programming (MILP) benchmark reduces NPC by 7.51% under baseline replacement accounting. The selected designs reveal a trade-off between cost and critical-load service. Planning decisions should therefore consider critical-load interruptions alongside annual LPSP.

Next EnergyVol. 14
University of Gonabad (IR)
Microgrid Control and Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon
Long-term capacity planning of a campus microgrid with flexible pumping demand and outage-aware rule-based energy management — Amin Ranjbaran · Next Energy (2026) | TGRS Research Map | TGRS