Approved, not yet begun: a dated cost forecast for Vietnam's North–South high-speed railway

In November 2024 Vietnam's National Assembly approved a 1,541 km high-speed railway from Hanoi to Ho Chi Minh City at a preliminary total investment of VND 1,713,548 billion, about USD 67.34 billion. The feasibility study was let in November 2026 and construction is now targeted for late 2028, two years later than first planned. This paper records two answers before construction begins. On how much, the cost growth of 31 completed and current railways, applied to the approved figure, gives USD 93bn in the middle case, USD 134bn at P80 and USD 178bn at P90, in money of the day. Only 3 of the 31 finished at or under budget. On where, a twelve-risk network built by written rules from the same railways puts the crossroads at price escalation: protecting its three links removes 37% of the cost that comes from risks setting each other off, and escalation into the viaducts is the most valuable single link. The crossroads holds in 12 of 12 robustness tests and under a second, route-length rule, but not under two alternative scope splits, which I report. The paper ends with three claims that can be checked as the project moves. Deposited with this record: the working paper (PDF), the rule-built register with live formulas. The views expressed are the author's own and not those of any employer or client.

Authors

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2026-11-26
DOI
https://doi.org/10.5281/zenodo.24553039
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Approved, not yet begun: a dated cost forecast for Vietnam's North–South high-speed railway

Nikhil Dhand
Zenodo (CERN European Organization for Nuclear Research)
Construction Project Management and Performance
article

Approved, not yet begun: a dated cost forecast for Vietnam's North–South high-speed railway

Nikhil Dhand
article en

Abstract

In November 2024 Vietnam's National Assembly approved a 1,541 km high-speed railway from Hanoi to Ho Chi Minh City at a preliminary total investment of VND 1,713,548 billion, about USD 67.34 billion. The feasibility study was let in November 2026 and construction is now targeted for late 2028, two years later than first planned. This paper records two answers before construction begins. On how much, the cost growth of 31 completed and current railways, applied to the approved figure, gives USD 93bn in the middle case, USD 134bn at P80 and USD 178bn at P90, in money of the day. Only 3 of the 31 finished at or under budget. On where, a twelve-risk network built by written rules from the same railways puts the crossroads at price escalation: protecting its three links removes 37% of the cost that comes from risks setting each other off, and escalation into the viaducts is the most valuable single link. The crossroads holds in 12 of 12 robustness tests and under a second, route-length rule, but not under two alternative scope splits, which I report. The paper ends with three claims that can be checked as the project moves. Deposited with this record: the working paper (PDF), the rule-built register with live formulas. The views expressed are the author's own and not those of any employer or client.

Zenodo (CERN European Organization for Nuclear Research)
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon