Before the first shovel: a dated cost forecast for Alto, the Toronto–Québec City high-speed line
Canada plans a high-speed railway of about 1,000 km from Toronto to Québec City, with construction of the first segment, Ottawa–Montréal, due to begin in 2029. The Government puts the cost at CAD 60–90 billion. In October 2026 the Parliamentary Budget Officer, working from 94 high-speed lines worldwide, put it at CAD 75–113 billion. This paper records two answers before construction starts. On how much, the cost growth of 31 completed and current railways, applied to the CAD 75 billion midpoint, gives CAD 104bn in the middle case and CAD 149bn at P80, in money of the day. Only 6 of the 31 grew by 20% or less, which is what staying inside CAD 90 billion would require. On where, a twelve-risk network built by written rules from the same railways puts the crossroads at the ordinary line works, not at the much-discussed tunnel under Mount Royal. Protecting the line works' six links removes 50% of the cost that comes from risks setting each other off, and the result holds in 12 of 12 robustness tests. Under one alternative scope split the tunnel edges ahead by a single point, and I report that. The paper ends with three claims that can be checked as the project moves. Deposited with this record: the working paper (PDF), the rule-built register with live formulas. The views expressed are the author's own and not those of any employer or clien.
Authors
- Nikhil Dhand (ORCID: https://orcid.org/0009-0000-6526-8399)
Publication Details
- Journal
- Zenodo (CERN European Organization for Nuclear Research)
- Published
- 2026-11-26
- DOI
- https://doi.org/10.5281/zenodo.24552461
- Primary Topic
- Construction Project Management and Performance
- Type
- article
- Field-Weighted Citation Impact
- 0.00