When a Temporary Bypass Becomes the Bottleneck: Machine Learning and Discrete-Event Simulation for Scheduling Water Main Rehabilitation
Rehabilitating small water mains by cement mortar lining or cured-in-place pipe usually keeps customers supplied through a temporary bypass. Bypass kits are scarce and must be cleaned and moved between streets, so releasing a kit at one site becomes a predecessor of work at another. A quantile regression forest was trained on a synthetic 10-year history of 480 sites calibrated to published utility documents. On a chronological hold-out of 144 sites it reduced mean pinball loss by 9% against historical distributions by work type, and its 90th percentile covered 87.5% of outcomes, against 21.5% for planned durations. In a discrete-event simulation of 1,000 ten-site programmes, better forecasts raised the probability that every kit was released on time from 0.293 to 0.329, and resequencing that protected every waiting site raised it to 0.344; protecting only the next site lowered it to 0.225. A lower booking confidence added 7 to 11 percentage points, and one extra kit added 15 to 17. Customer-hours of interruption varied by under 2% across policies. Results are scenario findings, not utility estimates.
Authors
- Prince Keshi
Publication Details
- Journal
- Iconic Research and Engineering Journals
- Published
- 2026-11-26
- DOI
- https://doi.org/10.64388/ire1725698
- Primary Topic
- Water Systems and Optimization
- Type
- article
- Field-Weighted Citation Impact
- 0.00