Qualitative and Quantitative Risk Techniques as Joint Predictors of Project Performance

Construction risk management is often studied as a choice between qualitative judgement and quantitative analysis, yet the practical question for project leaders is whether the two are jointly useful rather than mutually exclusive. This mixed-methods study tests whether qualitative and quantitative risk-management techniques are independent, positive predictors of reported project performance among construction professionals in Abuja, Nigeria, using 138 survey responses and ten semi-structured interviews from four purposively selected firms. A regression model confirms that qualitative techniques (beta = 0.395, p < 0.001) and quantitative techniques (beta = 0.361, p < 0.001) each retain a significant, independent association with reported performance after accounting for their shared variance, jointly explaining 40.2% of the variance (R2 = 0.402, F(2,135) = 45.36, p < 0.001). A hierarchical regression confirms this contribution holds after controlling for firm, formality and tool-use variables. Paired-samples tests further show that qualitative techniques and formal approaches are reported more extensively than quantitative techniques and informal approaches respectively, while traditional and digital tools do not differ significantly in their overall ratings, evidence that these practices coexist as complementary resources rather than substitute stages on a maturity ladder. Interview accounts explain the mechanism: qualitative techniques and informal consultation support rapid, judgement-based response to emerging site conditions, while quantitative techniques and formal procedures support disciplined analysis, accountability and traceability. The cross-sectional, single-source design does not establish causal effects or verify project outcomes independently. The findings give project leaders, professional bodies and researchers direct empirical evidence that investment in quantitative analytical capability need not come at the expense of qualitative judgement, and a basis for prioritising more rigorous confirmatory research across comparable project environments.

Authors

Institutions

Publication Details

Journal
IIARD INTERNATIONAL JOURNAL OF ECONOMICS AND BUSINESS MANAGEMENT
Published
2026-11-26
DOI
https://doi.org/10.56201/ijebm.vol.12.no11.2026.pg54.72
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Qualitative and Quantitative Risk Techniques as Joint Predictors of Project Performance

Okpe Christian Onuh
IIARD INTERNATIONAL JOURNAL OF ECONOMICS AND BUSINESS MANAGEMENT
Construction Project Management and Performance
article

Qualitative and Quantitative Risk Techniques as Joint Predictors of Project Performance

Okpe Christian Onuh
article en

Abstract

Construction risk management is often studied as a choice between qualitative judgement and quantitative analysis, yet the practical question for project leaders is whether the two are jointly useful rather than mutually exclusive. This mixed-methods study tests whether qualitative and quantitative risk-management techniques are independent, positive predictors of reported project performance among construction professionals in Abuja, Nigeria, using 138 survey responses and ten semi-structured interviews from four purposively selected firms. A regression model confirms that qualitative techniques (beta = 0.395, p < 0.001) and quantitative techniques (beta = 0.361, p < 0.001) each retain a significant, independent association with reported performance after accounting for their shared variance, jointly explaining 40.2% of the variance (R2 = 0.402, F(2,135) = 45.36, p < 0.001). A hierarchical regression confirms this contribution holds after controlling for firm, formality and tool-use variables. Paired-samples tests further show that qualitative techniques and formal approaches are reported more extensively than quantitative techniques and informal approaches respectively, while traditional and digital tools do not differ significantly in their overall ratings, evidence that these practices coexist as complementary resources rather than substitute stages on a maturity ladder. Interview accounts explain the mechanism: qualitative techniques and informal consultation support rapid, judgement-based response to emerging site conditions, while quantitative techniques and formal procedures support disciplined analysis, accountability and traceability. The cross-sectional, single-source design does not establish causal effects or verify project outcomes independently. The findings give project leaders, professional bodies and researchers direct empirical evidence that investment in quantitative analytical capability need not come at the expense of qualitative judgement, and a basis for prioritising more rigorous confirmatory research across comparable project environments.

IIARD INTERNATIONAL JOURNAL OF ECONOMICS AND BUSINESS MANAGEMENT
Nasarawa State University (NG)
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon
Qualitative and Quantitative Risk Techniques as Joint Predictors of Project Performance — Okpe Christian Onuh · IIARD INTERNATIONAL JOURNAL OF ECONOMICS AND BUSINESS MANAGEMENT (2026) | TGRS Research Map | TGRS