Half built and nearly doubled: a dated cost forecast for the Mumbai–Ahmedabad high-speed line

India's first high-speed railway, the 508 km line from Mumbai to Ahmedabad, was sanctioned at ₹1.08 lakh crore. In January 2026 the Railway Board put the likely cost at ₹1.98 lakh crore, and in August 2026 a revised estimate of about ₹2.1 lakh crore went to the Union Cabinet. The line is now about half built. This paper asks two questions and records the answers before the outcome is known. How much will it finally cost? And where in the project does risk travel? For the first I use three views of the same register of 100 transport megaprojects: the growth of 31 completed and current railways from their budgets, the railways that grew as much as this one already has, and what happened to projects after an estimate made part-way through construction. The views agree that ₹2.1 lakh crore is more likely to be passed than not. The central reading is about ₹2.19 lakh crore and the 80th percentile about ₹2.86 lakh crore, with a heavy upper tail. For the second I build a twelve-risk cost network by written rules from the same railways. Price escalation is the crossroads: protecting its three links removes 38% of the cost that comes from risks setting each other off, and the single most valuable link is escalation into the viaducts. That link stays first under every scope split I tried, but the crossroads itself does not, and I report that weakness rather than hide it. The paper ends with three claims that can be checked as the project moves. Deposited with this record: the working paper (PDF), the rule-built register with live formulas. The views expressed are the author's own and not those of any employer or client.

Authors

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2026-11-26
DOI
https://doi.org/10.5281/zenodo.24552690
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Half built and nearly doubled: a dated cost forecast for the Mumbai–Ahmedabad high-speed line

Nikhil Dhand
Zenodo (CERN European Organization for Nuclear Research)
Construction Project Management and Performance
article

Half built and nearly doubled: a dated cost forecast for the Mumbai–Ahmedabad high-speed line

Nikhil Dhand
article en

Abstract

India's first high-speed railway, the 508 km line from Mumbai to Ahmedabad, was sanctioned at ₹1.08 lakh crore. In January 2026 the Railway Board put the likely cost at ₹1.98 lakh crore, and in August 2026 a revised estimate of about ₹2.1 lakh crore went to the Union Cabinet. The line is now about half built. This paper asks two questions and records the answers before the outcome is known. How much will it finally cost? And where in the project does risk travel? For the first I use three views of the same register of 100 transport megaprojects: the growth of 31 completed and current railways from their budgets, the railways that grew as much as this one already has, and what happened to projects after an estimate made part-way through construction. The views agree that ₹2.1 lakh crore is more likely to be passed than not. The central reading is about ₹2.19 lakh crore and the 80th percentile about ₹2.86 lakh crore, with a heavy upper tail. For the second I build a twelve-risk cost network by written rules from the same railways. Price escalation is the crossroads: protecting its three links removes 38% of the cost that comes from risks setting each other off, and the single most valuable link is escalation into the viaducts. That link stays first under every scope split I tried, but the crossroads itself does not, and I report that weakness rather than hide it. The paper ends with three claims that can be checked as the project moves. Deposited with this record: the working paper (PDF), the rule-built register with live formulas. The views expressed are the author's own and not those of any employer or client.

Zenodo (CERN European Organization for Nuclear Research)
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon