A Robust Optimization Framework for Energy System Capacity Expansion under Line Outage Uncertainty

Capacity expansion models are widely used in climate and energy policy analysis to find optimal investments in generation, storage, and transmission. As the share of renewable generation grows, these models rely more on transmission lines to balance supply and demand across regions. Transmission lines, however, can fail due to aging, extreme weather, or accidents. Models that represent outages as time-dependent events come mainly from electrical engineering and are applied to small-scale systems, as they quickly become computationally intractable for inter-regional capacity expansion. We develop a capacity expansion model in which the risk of line failures shapes the investments in all parts of the system. We formulate it as a two-stage, scenario-based robust optimization problem that samples time-varying outage scenarios from a Markov model and hedges the investments against the most severe ones. To solve the model, we propose a memory-augmented Benders decomposition algorithm combined with Monte Carlo simulation that can handle thousands of scenarios. The selected plan is then evaluated with an out-of-sample simulation to bound the Value-at-Risk (VaR) of its system cost. In a 25-node case study of Germany and its neighboring countries, the gap between the lower bound and the simulated VaR bound is below 1%. We compare the robust plans with a deterministic plan, which assumes all lines are always available, and with a reserve-margin heuristic, which requires local firm capacity to be above peak demand. Like the heuristic, the robust plans nearly eliminate loss of load in 1000 simulated outage scenarios. Their mean system cost is within 0.2% of the deterministic plan and about 4.5% below the heuristic. Instead of adding more generation capacity, the robust approach mainly changes the type and location of capacity, for example, by spreading storage across the network.

Authors

Publication Details

Journal
arXiv
Published
2026-11-25
DOI
https://doi.org/10.48550/arxiv.2611.34113
Primary Topic
Electric Power System Optimization
Type
preprint
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
preprint

A Robust Optimization Framework for Energy System Capacity Expansion under Line Outage Uncertainty

Kamran Forghani, Fredrik Hedenus, Iegor Riepin, Lina Reichenberg
arXiv
Electric Power System Optimization
preprint

A Robust Optimization Framework for Energy System Capacity Expansion under Line Outage Uncertainty

Kamran Forghani, Fredrik Hedenus, Iegor Riepin, Lina Reichenberg
preprint en

Abstract

Capacity expansion models are widely used in climate and energy policy analysis to find optimal investments in generation, storage, and transmission. As the share of renewable generation grows, these models rely more on transmission lines to balance supply and demand across regions. Transmission lines, however, can fail due to aging, extreme weather, or accidents. Models that represent outages as time-dependent events come mainly from electrical engineering and are applied to small-scale systems, as they quickly become computationally intractable for inter-regional capacity expansion. We develop a capacity expansion model in which the risk of line failures shapes the investments in all parts of the system. We formulate it as a two-stage, scenario-based robust optimization problem that samples time-varying outage scenarios from a Markov model and hedges the investments against the most severe ones. To solve the model, we propose a memory-augmented Benders decomposition algorithm combined with Monte Carlo simulation that can handle thousands of scenarios. The selected plan is then evaluated with an out-of-sample simulation to bound the Value-at-Risk (VaR) of its system cost. In a 25-node case study of Germany and its neighboring countries, the gap between the lower bound and the simulated VaR bound is below 1%. We compare the robust plans with a deterministic plan, which assumes all lines are always available, and with a reserve-margin heuristic, which requires local firm capacity to be above peak demand. Like the heuristic, the robust plans nearly eliminate loss of load in 1000 simulated outage scenarios. Their mean system cost is within 0.2% of the deterministic plan and about 4.5% below the heuristic. Instead of adding more generation capacity, the robust approach mainly changes the type and location of capacity, for example, by spreading storage across the network.

arXiv
Electric Power System Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon