Responsibility Allocation and Delay Mitigation Strategies in Owner-Initiated Changes in Ethiopia: A Case Study of the Nyala Insurance Headquarters Building Project

Owner-initiated changes are a major source of construction delays, particularly when design revisions occur after construction and procurement activities have commenced. This study examines responsibility allocation and delay-mitigation strategies for owner-initiated changes in the Nyala Insurance Headquarters Building Project, a 3B + G+18 commercial building in Addis Ababa, Ethiopia. A qualitative case-study design integrating project records, stakeholder interviews, informal discussions, and site observations was adopted. Data were analyzed using thematic content analysis and descriptive statistics. The findings identified 50 recorded delay occurrences, with owner-initiated changes accounting for the largest contribution (38%), followed by design review and approval delays (24%), material procurement (18%), payment delays (12%), and external factors (8%). The average reported delay contribution was 26 days. Among the identified changes, MEP modifications recorded the highest frequency (7) and average delay (60 days), followed by curtain wall changes (5; 45 days), interior works (4; 30 days), and structural modifications (3; 20 days). The project also recorded ETB 95 million in outstanding payments against ETB 430 million in listed payment categories. Although change orders were fully implemented, monitoring and reporting achieved only 50% implementation. The study demonstrates the importance of early design finalization, clear accountability, coordinated procurement, and proactive schedule monitoring.

Authors

Institutions

Publication Details

Journal
Research Square
Published
2026-11-26
DOI
https://doi.org/10.21203/rs.3.rs-11869481/v1
Primary Topic
Construction Project Management and Performance
Type
preprint
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
preprint

Responsibility Allocation and Delay Mitigation Strategies in Owner-Initiated Changes in Ethiopia: A Case Study of the Nyala Insurance Headquarters Building Project

Zenagebriel Gebremedhn
Research Square
Construction Project Management and Performance
preprint

Responsibility Allocation and Delay Mitigation Strategies in Owner-Initiated Changes in Ethiopia: A Case Study of the Nyala Insurance Headquarters Building Project

Zenagebriel Gebremedhn
preprint en

Abstract

Owner-initiated changes are a major source of construction delays, particularly when design revisions occur after construction and procurement activities have commenced. This study examines responsibility allocation and delay-mitigation strategies for owner-initiated changes in the Nyala Insurance Headquarters Building Project, a 3B + G+18 commercial building in Addis Ababa, Ethiopia. A qualitative case-study design integrating project records, stakeholder interviews, informal discussions, and site observations was adopted. Data were analyzed using thematic content analysis and descriptive statistics. The findings identified 50 recorded delay occurrences, with owner-initiated changes accounting for the largest contribution (38%), followed by design review and approval delays (24%), material procurement (18%), payment delays (12%), and external factors (8%). The average reported delay contribution was 26 days. Among the identified changes, MEP modifications recorded the highest frequency (7) and average delay (60 days), followed by curtain wall changes (5; 45 days), interior works (4; 30 days), and structural modifications (3; 20 days). The project also recorded ETB 95 million in outstanding payments against ETB 430 million in listed payment categories. Although change orders were fully implemented, monitoring and reporting achieved only 50% implementation. The study demonstrates the importance of early design finalization, clear accountability, coordinated procurement, and proactive schedule monitoring.

Research Square
Mekelle University (ET)
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon