Time-Based Reconstruction, Uncertainty Assessment, and Prediction of Concurrent Water Supply Interruptions and Repair Work for Maintenance Engineering
Weekly counts and total durations can conceal overlapping water supply interruptions and repair work. Using 4885 entries from a municipal utility database in southeastern Poland (2004–2025), we assess aggregation loss (RQ1), sensitivity of reconstructed overlap (RQ2) and predictive reliability for maintenance planning (RQ3). Among 56 groups of weeks with identical counts and accumulated interruption and repair-work durations, 40 contain weeks differing in peak concurrency or threshold exposure. Associated repair work remains active at restoration in 96.86% of interruption episodes. The repair-work maximum of nine is reproduced by every fixed-count reference path. In separate sensitivity analyses, the maximum falls to seven after hypothetical grouping and to four after excluding 2007. The full-database maximum remains nine under endpoint changes of up to 30 min within recorded dates. OR (1,2) exposure spans 683.92–1572.25 h around 1061.42 h nominally. Five simulators show uneven calibration across January, April, July and October origins. For nominal 90% prediction intervals, the five-year-donor NB2 model covers 62.5% of monthly counts in the frozen assessment and 28.6% of annual counts across 14 January origins. Chronology supports audits of concentrated work and restoration timing; staffing decisions require verified job identifiers and resource data.
Authors
- Katarzyna Pietrucha-Urbanik (ORCID: https://orcid.org/0000-0003-1160-9009)
- Barbara Tchórzewska-Cieślak (ORCID: https://orcid.org/0000-0002-7622-6749)
- Mohamed Eid (ORCID: https://orcid.org/0000-0002-8274-3005)
Institutions
- Rzeszów University of Technology (PL)
Publication Details
- Journal
- Applied Sciences
- Published
- 2026-11-25
- DOI
- https://doi.org/10.3390/app162311671
- Primary Topic
- Water Systems and Optimization
- Type
- article
- Field-Weighted Citation Impact
- 0.00