Reducing Material Overordering in UK Construction Projects: A NetLogo Study of Procurement Under Schedule Uncertainty
Ordering more material than a job needs (material overordering) can protect installation work from shortages, but it can also leave costly stock at handover. This study examines how that trade-off changes when a construction buyer revises purchase orders against a shifting work schedule. A NetLogo 7.0.4 agent-based model represents a buyer, a supplier, two installation crews, 24 work packages and an order pipeline. A fully crossed BehaviorSpace experiment compares padded bulk buying, two standard rolling order rules and a rolling policy that caps its target at remaining demand.