Integrated Field Control Protocol for Disaster Recovery Works on Transportation Infrastructure (IFCP-DR)

Recovery of transportation infrastructure after hurricanes, floods and landslides combines evolving scope,weather variability, work under traffic and public funding that requires a reliable record of what was done, what itcost and why. U.S. oversight bodies have documented weaknesses precisely in this layer: undocumenteddecisions, contractor performance not recorded, invoices that do not match contract terms and permanent repairsdelayed by design changes and construction delays. The IFCP-DR is a method for managing the execution ofthese works. It follows one operational logic (field, control, management, evidence and learning) and is organizedin three levels: essential controls, mandatory in every contract; a management routine; and improvement toolsapplied when needed. It integrates project management practice (PMBOK Guide, 8th edition, the ten knowledgeareas of the 6th edition and the Construction Extension), Lean Six Sigma and statistical process control, and fielddocumentation practice. It defines a six-phase lifecycle with six control gates, a traceability chain with a procedurefor pending evidence, a change control flow, twelve field record templates, an indicator dictionary with limitations,statistical rules for reading variation, a toolkit tied to the decisions it supports, management routines, fourimplementation stages with criteria for the pilot, its evaluation and expansion, a maturity model, a trainingcurriculum, a validation matrix, a contractual authority matrix, a worked example with filled records and analignment matrix that separates official requirements and audit findings from the internal controls of the protocol. Itderives from the emergency recovery of a mountain highway in Brazil, documented in an open access case study

Authors

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2026-11-24
DOI
https://doi.org/10.5281/zenodo.24529697
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Integrated Field Control Protocol for Disaster Recovery Works on Transportation Infrastructure (IFCP-DR)

Emanuel Augusto Valle
Zenodo (CERN European Organization for Nuclear Research)
Construction Project Management and Performance
article

Integrated Field Control Protocol for Disaster Recovery Works on Transportation Infrastructure (IFCP-DR)

Emanuel Augusto Valle
article en

Abstract

Recovery of transportation infrastructure after hurricanes, floods and landslides combines evolving scope,weather variability, work under traffic and public funding that requires a reliable record of what was done, what itcost and why. U.S. oversight bodies have documented weaknesses precisely in this layer: undocumenteddecisions, contractor performance not recorded, invoices that do not match contract terms and permanent repairsdelayed by design changes and construction delays. The IFCP-DR is a method for managing the execution ofthese works. It follows one operational logic (field, control, management, evidence and learning) and is organizedin three levels: essential controls, mandatory in every contract; a management routine; and improvement toolsapplied when needed. It integrates project management practice (PMBOK Guide, 8th edition, the ten knowledgeareas of the 6th edition and the Construction Extension), Lean Six Sigma and statistical process control, and fielddocumentation practice. It defines a six-phase lifecycle with six control gates, a traceability chain with a procedurefor pending evidence, a change control flow, twelve field record templates, an indicator dictionary with limitations,statistical rules for reading variation, a toolkit tied to the decisions it supports, management routines, fourimplementation stages with criteria for the pilot, its evaluation and expansion, a maturity model, a trainingcurriculum, a validation matrix, a contractual authority matrix, a worked example with filled records and analignment matrix that separates official requirements and audit findings from the internal controls of the protocol. Itderives from the emergency recovery of a mountain highway in Brazil, documented in an open access case study

Zenodo (CERN European Organization for Nuclear Research)
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon