System Dynamics Modelling for Performance Evaluation of Prefabricated Interspersed Construction

Prefabrication and interspersed (fast-tracking) scheduling are each known to improve construction productivity, yet their combined behaviour has rarely been modelled as a single dynamic system. In this study, a system dynamics (SD) model was built in Vensim to link the prefabrication ratio with interspersed scheduling across four subsystems: schedule, quality, management, and economic benefit. From 36 candidate factors identified in the literature, practitioner interviews, and site experience, 28 were retained through an exploratory factor analysis of 95 valid questionnaire responses (KMO = 0.701; Bartlett’s test significant) and used to screen and structure the indicators entering the model’s 74 equations. The model was simulated for a 28-storey residential case in Beijing over 12 months, and the stochastic flows were run as an ensemble of 100 simulations with different seeds, which places a 5–95% envelope of at most 0.22 index points on the composite trajectory. A one-at-a-time sensitivity analysis shows that the stage ranking is scale-dependent: decoration leads by a factor of 3.9 on the model’s native index but becomes the weakest of the four stages once the stocks are placed on a common scale, so no stage priority is claimed. A numerical sweep of the prefabrication ratio from 0.20 to 0.80 changes total construction cost by −5.9% to +8.9% relative to the case value of 0.50 but moves the composite index by less than 0.5%, which locates the leverage of the ratio in the cost channel rather than in the schedule channel. Formal predictive validation against measured project records is not reported here and is identified as the principal limitation and next step.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2026-11-24
DOI
https://doi.org/10.3390/buildings16234684
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

System Dynamics Modelling for Performance Evaluation of Prefabricated Interspersed Construction

杜慧, Yu Diao, Jing Du
2 links
Buildings
BIM and Construction Integration
article

System Dynamics Modelling for Performance Evaluation of Prefabricated Interspersed Construction

杜慧, Yu Diao, Jing Du
article en

Abstract

Prefabrication and interspersed (fast-tracking) scheduling are each known to improve construction productivity, yet their combined behaviour has rarely been modelled as a single dynamic system. In this study, a system dynamics (SD) model was built in Vensim to link the prefabrication ratio with interspersed scheduling across four subsystems: schedule, quality, management, and economic benefit. From 36 candidate factors identified in the literature, practitioner interviews, and site experience, 28 were retained through an exploratory factor analysis of 95 valid questionnaire responses (KMO = 0.701; Bartlett’s test significant) and used to screen and structure the indicators entering the model’s 74 equations. The model was simulated for a 28-storey residential case in Beijing over 12 months, and the stochastic flows were run as an ensemble of 100 simulations with different seeds, which places a 5–95% envelope of at most 0.22 index points on the composite trajectory. A one-at-a-time sensitivity analysis shows that the stage ranking is scale-dependent: decoration leads by a factor of 3.9 on the model’s native index but becomes the weakest of the four stages once the stocks are placed on a common scale, so no stage priority is claimed. A numerical sweep of the prefabrication ratio from 0.20 to 0.80 changes total construction cost by −5.9% to +8.9% relative to the case value of 0.50 but moves the composite index by less than 0.5%, which locates the leverage of the ratio in the cost channel rather than in the schedule channel. Formal predictive validation against measured project records is not reported here and is identified as the principal limitation and next step.

BuildingsVol. 16(23)
Tianjin University (CN), Shenzhen Polytechnic University (CN)
National Natural Science Foundation of China
Industry, innovation and infrastructure
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon