Schedule Risk Analysis and Recovery Planning for Large-Scale Entertainment Projects in Saudi Arabia

Large entertainment developments combine conventional building works with specialist equipment, controls integration, commissioning and operator mobilisation. A schedule can show physical progress while the activities required for a safe opening fall behind. This paper develops a schedule risk and recovery framework for Saudi entertainment projects through a structured narrative synthesis of Saudi construction delay research, project scheduling literature and professional guidance. It links the contractual baseline to a logic driven current forecast, then connects risk drivers and opening dependencies to specific recovery decisions. An illustrative network compares a delayed forecast with procurement acceleration, site resequencing and coordinated recovery. The example shows how a supplier intervention can move the critical path to utility readiness and how a larger recovery package can improve the likelihood of a target while leaving substantial residual exposure. The proposed approach preserves commissioning and acceptance requirements, assigns accountability for cross package handovers and retains auditable programme versions. Its contribution is a decision sequence that connects construction progress, milestone risk and operational readiness in the same planning process.

Authors

Publication Details

Journal
Iconic Research and Engineering Journals
Published
2026-11-24
DOI
https://doi.org/10.64388/ire1725647
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Schedule Risk Analysis and Recovery Planning for Large-Scale Entertainment Projects in Saudi Arabia

Pavithran Ravikumar
4 links
Iconic Research and Engineering Journals
Construction Project Management and Performance
article

Schedule Risk Analysis and Recovery Planning for Large-Scale Entertainment Projects in Saudi Arabia

Pavithran Ravikumar
article en

Abstract

Large entertainment developments combine conventional building works with specialist equipment, controls integration, commissioning and operator mobilisation. A schedule can show physical progress while the activities required for a safe opening fall behind. This paper develops a schedule risk and recovery framework for Saudi entertainment projects through a structured narrative synthesis of Saudi construction delay research, project scheduling literature and professional guidance. It links the contractual baseline to a logic driven current forecast, then connects risk drivers and opening dependencies to specific recovery decisions. An illustrative network compares a delayed forecast with procurement acceleration, site resequencing and coordinated recovery. The example shows how a supplier intervention can move the critical path to utility readiness and how a larger recovery package can improve the likelihood of a target while leaving substantial residual exposure. The proposed approach preserves commissioning and acceptance requirements, assigns accountability for cross package handovers and retains auditable programme versions. Its contribution is a decision sequence that connects construction progress, milestone risk and operational readiness in the same planning process.

Iconic Research and Engineering JournalsVol. 10(5)
Industry, innovation and infrastructure
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon
Schedule Risk Analysis and Recovery Planning for Large-Scale Entertainment Projects in Saudi Arabia — Pavithran Ravikumar · Iconic Research and Engineering Journals (2026) | TGRS Research Map | TGRS