Effects of Right-of-Way Clearance on Cost and Schedule Performance of Road Construction Projects in Ethiopia: A Case Study of the Sodo–Tercha Road Project

Right-of-way (ROW) clearance is a critical precondition for uninterrupted road construction, yet land acquisition, compensation, utility relocation, and site handover can delay project delivery. This study assessed the effects of ROW clearance on cost and schedule performance in the 75.72-km Sodo–Tercha Road Upgrading Project, Lot 1 (Sodo–Omo River section), Ethiopia. A mixed-methods case-study design integrated 84 structured questionnaires, 10 key-informant interviews, field observations, and project-document analysis. Quantitative responses were examined using descriptive statistics and the Relative Importance Index (RII), while interview evidence was thematically analyzed. Project records showed that the planned duration of 1,260 days increased to 2,067 days, a delay of 807 days (64.05%). Of the 807-day extension, 642 days were attributed to ROW-related obstructions, equivalent to approximately 79.6%. Utility relocation increased from 2 to 11 months, and compensation payment increased from 2 to 9 months. The contract sum rose from ETB 1,328,412,050 to ETB 1,383,400,809, representing a 4.14% increase; reported price-adjustment payments totaled ETB 129.79 million. Overhead costs (RII = 0.863), contractor claims (0.850), and idle labour/equipment (0.819) were the highest-ranked cost effects. Extension of time (0.975) and out-of-sequence work (0.913) dominated schedule effects. The findings demonstrate the importance of securing land and coordinating utility relocation before construction mobilization.

Authors

Institutions

Publication Details

Journal
Research Square
Published
2026-11-23
DOI
https://doi.org/10.21203/rs.3.rs-11795107/v1
Primary Topic
Construction Project Management and Performance
Type
preprint
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
preprint

Effects of Right-of-Way Clearance on Cost and Schedule Performance of Road Construction Projects in Ethiopia: A Case Study of the Sodo–Tercha Road Project

Zenagebriel Gebremedhn
Research Square
Construction Project Management and Performance
preprint

Effects of Right-of-Way Clearance on Cost and Schedule Performance of Road Construction Projects in Ethiopia: A Case Study of the Sodo–Tercha Road Project

Zenagebriel Gebremedhn
preprint en

Abstract

Right-of-way (ROW) clearance is a critical precondition for uninterrupted road construction, yet land acquisition, compensation, utility relocation, and site handover can delay project delivery. This study assessed the effects of ROW clearance on cost and schedule performance in the 75.72-km Sodo–Tercha Road Upgrading Project, Lot 1 (Sodo–Omo River section), Ethiopia. A mixed-methods case-study design integrated 84 structured questionnaires, 10 key-informant interviews, field observations, and project-document analysis. Quantitative responses were examined using descriptive statistics and the Relative Importance Index (RII), while interview evidence was thematically analyzed. Project records showed that the planned duration of 1,260 days increased to 2,067 days, a delay of 807 days (64.05%). Of the 807-day extension, 642 days were attributed to ROW-related obstructions, equivalent to approximately 79.6%. Utility relocation increased from 2 to 11 months, and compensation payment increased from 2 to 9 months. The contract sum rose from ETB 1,328,412,050 to ETB 1,383,400,809, representing a 4.14% increase; reported price-adjustment payments totaled ETB 129.79 million. Overhead costs (RII = 0.863), contractor claims (0.850), and idle labour/equipment (0.819) were the highest-ranked cost effects. Extension of time (0.975) and out-of-sequence work (0.913) dominated schedule effects. The findings demonstrate the importance of securing land and coordinating utility relocation before construction mobilization.

Research Square
Mekelle University (ET)
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon
Effects of Right-of-Way Clearance on Cost and Schedule Performance of Road Construction Projects in Ethiopia: A Case Study of the Sodo–Tercha Road Project — Zenagebriel Gebremedhn · Research Square (2026) | TGRS Research Map | TGRS