Critical Path Method Adoption, Delay Factors and Schedule Crashing in Lagos Construction Projects: A Survey and a Proposed Six-Stage Framework

Background: Construction projects in Lagos State often finish late, although the Critical Path Method (CPM) is well established. Earlier Lagos studies ranked causes of delay but did not measure CPM adoption, delay on critical activities and the judged effectiveness of crashing in one sample. Methods: A cross-sectional questionnaire survey was carried out among engineers, builders, project managers and architects working in four Lagos local government areas. Of 250 questionnaires distributed, 99 were returned (39.6%), and 83 to 96 responses were valid for each analysis. Data were analysed with descriptive statistics, the Relative Importance Index, one-sample t-tests, Pearson correlation and one-way ANOVA. Results: CPM adoption (M = 3.72, SD = 0.90) and perceived crashing effectiveness (M = 3.61, SD = 0.77) were above the scale midpoint, with large effects (d ≈ 0.80). Among 16 delay factors, labour shortages and low productivity (M = 3.64), bad weather, design changes, equipment constraints and governance issues ranked highest. Agreement that compression follows cost-benefit analysis was only moderate (M = 3.41), and perceived crashing effectiveness was unrelated to adoption (r = .15, p = .156). Early contractor involvement (M = 4.09) was the most supported strategy. Conclusion: Lagos professionals report wide use of CPM, but training and cost-based recovery decisions are weak points. A six-stage framework is proposed for validation. The findings rest on perceptions from a non-probability sample and do not show that CPM reduces delay.

Authors

Institutions

Publication Details

Journal
Iconic Research and Engineering Journals
Published
2026-11-19
DOI
https://doi.org/10.64388/ire1725414
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Critical Path Method Adoption, Delay Factors and Schedule Crashing in Lagos Construction Projects: A Survey and a Proposed Six-Stage Framework

Akinwale Oladotun Coker, Yinka L. Ogunsola
Iconic Research and Engineering Journals
Construction Project Management and Performance
article

Critical Path Method Adoption, Delay Factors and Schedule Crashing in Lagos Construction Projects: A Survey and a Proposed Six-Stage Framework

Akinwale Oladotun Coker, Yinka L. Ogunsola
article en

Abstract

Background: Construction projects in Lagos State often finish late, although the Critical Path Method (CPM) is well established. Earlier Lagos studies ranked causes of delay but did not measure CPM adoption, delay on critical activities and the judged effectiveness of crashing in one sample. Methods: A cross-sectional questionnaire survey was carried out among engineers, builders, project managers and architects working in four Lagos local government areas. Of 250 questionnaires distributed, 99 were returned (39.6%), and 83 to 96 responses were valid for each analysis. Data were analysed with descriptive statistics, the Relative Importance Index, one-sample t-tests, Pearson correlation and one-way ANOVA. Results: CPM adoption (M = 3.72, SD = 0.90) and perceived crashing effectiveness (M = 3.61, SD = 0.77) were above the scale midpoint, with large effects (d ≈ 0.80). Among 16 delay factors, labour shortages and low productivity (M = 3.64), bad weather, design changes, equipment constraints and governance issues ranked highest. Agreement that compression follows cost-benefit analysis was only moderate (M = 3.41), and perceived crashing effectiveness was unrelated to adoption (r = .15, p = .156). Early contractor involvement (M = 4.09) was the most supported strategy. Conclusion: Lagos professionals report wide use of CPM, but training and cost-based recovery decisions are weak points. A six-stage framework is proposed for validation. The findings rest on perceptions from a non-probability sample and do not show that CPM reduces delay.

Iconic Research and Engineering JournalsVol. 10(5)
University of Ibadan (NG)
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon