N-1 Security constrained Hosting Capacity Assessment for Ultra Large-scale Data Center with Workload Flexibility

Transmission network security can substantially alter where large-scale data centers can connect and how much workload flexibility can unlock. This paper develops a hosting-capacity framework that couples computing demand, batch workload scheduling, and N-1 security constraints. A modified IEEE 118-bus case study reveals that two data center sites with identical hosting capacities under normal operation differ by 874.5 MW under the contingencies operation when workload flexibility is enabled. Six-hour batch deferral increases N-1 hosting capacity by up to 24.5\% relative to immediate execution. These gains arise from reducing demand at critical hours while accommodating deferred tasks within subsequent transmission limits and deadlines. At bus 92, a four-hour window captures 90.9\% of the six-hour capacity gain. The findings establish workload flexibility as a location-dependent connection resource whose capacity value requires joint assessment of contingency exposure and deadline constrainted workload recovery, beyond the power reduction available at a single critical hour.

Authors

Publication Details

Journal
arXiv (Cornell University)
Published
2026-11-18
DOI
https://doi.org/10.48550/arxiv.2611.24493
Primary Topic
Electric Power System Optimization
Type
preprint
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
preprint

N-1 Security constrained Hosting Capacity Assessment for Ultra Large-scale Data Center with Workload Flexibility

Pengyu Ren, Jiakai Wu, Wei Sun, Yifan Wang
arXiv (Cornell University)
Electric Power System Optimization
preprint

N-1 Security constrained Hosting Capacity Assessment for Ultra Large-scale Data Center with Workload Flexibility

Pengyu Ren, Jiakai Wu, Wei Sun, Yifan Wang
preprint en

Abstract

Transmission network security can substantially alter where large-scale data centers can connect and how much workload flexibility can unlock. This paper develops a hosting-capacity framework that couples computing demand, batch workload scheduling, and N-1 security constraints. A modified IEEE 118-bus case study reveals that two data center sites with identical hosting capacities under normal operation differ by 874.5 MW under the contingencies operation when workload flexibility is enabled. Six-hour batch deferral increases N-1 hosting capacity by up to 24.5\% relative to immediate execution. These gains arise from reducing demand at critical hours while accommodating deferred tasks within subsequent transmission limits and deadlines. At bus 92, a four-hour window captures 90.9\% of the six-hour capacity gain. The findings establish workload flexibility as a location-dependent connection resource whose capacity value requires joint assessment of contingency exposure and deadline constrainted workload recovery, beyond the power reduction available at a single critical hour.

arXiv (Cornell University)
Electric Power System Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon