Foundational Earned Value Management Techniques, Performance Index Techniques and Performance of Water and Sanitation Projects under Athi Water Works Development Agency, Kenya

Water and sanitation projects in Kenya continue to experience cost overruns, schedule delays and stakeholder dissatisfaction, despite substantial public and donor investment. Earned Value Management (EVM) integrates scope, schedule and cost into a single performance measurement system, yet its application in Kenyan water projects remains limited and insufficiently documented. This study examined the influence of two EVM techniques, foundational EVM techniques (Planned Value, Earned Value and Actual Cost) and EVM performance index techniques (Cost Performance Index and Schedule Performance Index), on the performance of water and sanitation projects under Athi Water Works Development Agency in Nairobi, Kiambu and Muranga counties. The study was anchored on project control theory. A descriptive cross-sectional survey design was adopted. Using Yamane's formula and stratified random sampling, 120 professionals were selected from a population of 170 project managers, engineers, site supervisors, procurement officers and government officials. Data were collected using a structured questionnaire, and 102 usable responses were obtained, a response rate of 85%. Data were analysed using descriptive statistics, Pearson correlation and multiple linear regression. Respondents agreed that foundational EVM techniques (M = 3.68, SD = 0.70) and performance index techniques (M = 3.66, SD = 0.68) were applied in their projects. Both techniques had strong, positive and significant relationships with project performance (r = 0.684 and r = 0.678, p < 0.001). Together, the two techniques explained 69.2% of the variance in project performance, F(2, 99) = 111.05, p < 0.001. Foundational EVM techniques (Beta = 0.512, p < 0.001) and performance index techniques (Beta = 0.503, p < 0.001) each made a significant unique contribution. The study concludes that clearly defined baselines and routine use of cost and schedule performance indices are associated with better project performance. It recommends training of project staff in EVM, consistent recording of Planned Value, Earned Value and Actual Cost, and the use of CPI and SPI in all project progress reports. Keywords: Earned Value Management, Cost Performance Index, Schedule Performance Index, Project Performance, Water and Sanitation Projects, Kenya

Authors

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2026-11-18
DOI
https://doi.org/10.5281/zenodo.24341932
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Foundational Earned Value Management Techniques, Performance Index Techniques and Performance of Water and Sanitation Projects under Athi Water Works Development Agency, Kenya

Paul Munene, Patricia Nyadhi Ochieng
1 links
Zenodo (CERN European Organization for Nuclear Research)
Construction Project Management and Performance
article

Foundational Earned Value Management Techniques, Performance Index Techniques and Performance of Water and Sanitation Projects under Athi Water Works Development Agency, Kenya

Paul Munene, Patricia Nyadhi Ochieng
article en

Abstract

Water and sanitation projects in Kenya continue to experience cost overruns, schedule delays and stakeholder dissatisfaction, despite substantial public and donor investment. Earned Value Management (EVM) integrates scope, schedule and cost into a single performance measurement system, yet its application in Kenyan water projects remains limited and insufficiently documented. This study examined the influence of two EVM techniques, foundational EVM techniques (Planned Value, Earned Value and Actual Cost) and EVM performance index techniques (Cost Performance Index and Schedule Performance Index), on the performance of water and sanitation projects under Athi Water Works Development Agency in Nairobi, Kiambu and Muranga counties. The study was anchored on project control theory. A descriptive cross-sectional survey design was adopted. Using Yamane's formula and stratified random sampling, 120 professionals were selected from a population of 170 project managers, engineers, site supervisors, procurement officers and government officials. Data were collected using a structured questionnaire, and 102 usable responses were obtained, a response rate of 85%. Data were analysed using descriptive statistics, Pearson correlation and multiple linear regression. Respondents agreed that foundational EVM techniques (M = 3.68, SD = 0.70) and performance index techniques (M = 3.66, SD = 0.68) were applied in their projects. Both techniques had strong, positive and significant relationships with project performance (r = 0.684 and r = 0.678, p < 0.001). Together, the two techniques explained 69.2% of the variance in project performance, F(2, 99) = 111.05, p < 0.001. Foundational EVM techniques (Beta = 0.512, p < 0.001) and performance index techniques (Beta = 0.503, p < 0.001) each made a significant unique contribution. The study concludes that clearly defined baselines and routine use of cost and schedule performance indices are associated with better project performance. It recommends training of project staff in EVM, consistent recording of Planned Value, Earned Value and Actual Cost, and the use of CPI and SPI in all project progress reports. Keywords: Earned Value Management, Cost Performance Index, Schedule Performance Index, Project Performance, Water and Sanitation Projects, Kenya

Zenodo (CERN European Organization for Nuclear Research)
Clean water and sanitation
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon