Project Schedule Optimization for Villa Development Using the Critical Path Method (CPM) and Line of Balance (LOB): A Case Study of the Indie Villa Development Project in Kuta

Project scheduling is a critical factor in ensuring timely completion, efficient resource utilization, and effective control of construction projects. Villa construction projects often involve repetitive activities, where conventional scheduling methods may not adequately address workflow continuity and resource coordination. This study aims to optimize the construction schedule of the Indie Villa Project by integrating the Critical Path Method (CPM) and the Line of Balance (LOB). A quantitative descriptive approach was applied using primary data collected through interviews with the project manager, site engineer, and field supervisor, supported by secondary data including project schedules, work breakdown structures, and progress reports. CPM was employed to identify critical activities and determine the project critical path, while LOB was applied to analyze repetitive activities and optimize crew movement among villa units. Schedule optimization was achieved through activity overlapping, resource leveling, and selective crashing. The results show that the original project duration of 526 days was successfully reduced to 345 days, saving 181 days or 34.41% without changing the project scope. The integrated CPM–LOB approach improved workflow continuity, reduced idle time, optimized resource utilization, and enhanced schedule control, demonstrating its effectiveness for repetitive villa construction projects.

Authors

Publication Details

Journal
Andalasian International Journal of Applied Science Engineering and Technology
Published
2026-11-17
DOI
https://doi.org/10.25077/aijaset.v6i3.359
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Project Schedule Optimization for Villa Development Using the Critical Path Method (CPM) and Line of Balance (LOB): A Case Study of the Indie Villa Development Project in Kuta

Jauhar Fajrin, Lalu Wisesa Grahita Ramdhani, Hariyadi Hariyadi
Andalasian International Journal of Applied Science Engineering and Technology
Resource-Constrained Project Scheduling
article

Project Schedule Optimization for Villa Development Using the Critical Path Method (CPM) and Line of Balance (LOB): A Case Study of the Indie Villa Development Project in Kuta

Jauhar Fajrin, Lalu Wisesa Grahita Ramdhani, Hariyadi Hariyadi
article en

Abstract

Project scheduling is a critical factor in ensuring timely completion, efficient resource utilization, and effective control of construction projects. Villa construction projects often involve repetitive activities, where conventional scheduling methods may not adequately address workflow continuity and resource coordination. This study aims to optimize the construction schedule of the Indie Villa Project by integrating the Critical Path Method (CPM) and the Line of Balance (LOB). A quantitative descriptive approach was applied using primary data collected through interviews with the project manager, site engineer, and field supervisor, supported by secondary data including project schedules, work breakdown structures, and progress reports. CPM was employed to identify critical activities and determine the project critical path, while LOB was applied to analyze repetitive activities and optimize crew movement among villa units. Schedule optimization was achieved through activity overlapping, resource leveling, and selective crashing. The results show that the original project duration of 526 days was successfully reduced to 345 days, saving 181 days or 34.41% without changing the project scope. The integrated CPM–LOB approach improved workflow continuity, reduced idle time, optimized resource utilization, and enhanced schedule control, demonstrating its effectiveness for repetitive villa construction projects.

Andalasian International Journal of Applied Science Engineering and TechnologyVol. 6(3)
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon