Mechanism of shallow hard-shell-layer formation for newly-reclaimed dredged silt using vacuum dewatering combined with preloading

Newly-reclaimed dredged silt sites present a critical geotechnical challenge immediately after hydraulic filling. The ground surface remains as fluidized mud, preventing personnel and equipment access, yet conventional treatment methods assume the site is already accessible. This paper proposes a vacuum dewatering combined with preloading (VDCP) method for rapid formation of a shallow hard-shell layer without sand cushions or prolonged drying. A three-dimensional horizontal–vertical drainage network is established, coupling free-water extraction and negative-pressure consolidation. Physical model tests on Xiamen dredged silt (initial water content 281%) and Plaxis 2D numerical simulations are conducted to investigate the reinforcement mechanisms during the hard-shell formation stage. After 1,188 h of vacuum extraction, the average water content of the shallow soil decreases to 58%, the void ratio reduces from 7.53 to 1.49, and the ultimate bearing capacity increases from near zero to over 40 kPa, meeting the requirements for personnel and light machinery access. Numerical comparisons demonstrate that the three-dimensional drainage system achieves approximately 61.0% excess pore water pressure dissipation within 1,200 h, compared with 22.4% for horizontal-only and 18.3% for vertical-only drainage, confirming the synergistic effect of combined drainage channels, although these ratios are semi-quantitative. A consolidation coupling effect between vacuum and surcharge is observed; however, surcharge should be applied only after the soil has gained sufficient shear strength. The VDCP method and the proposed phased treatment framework, which designates shallow hard-shell formation as an independent preliminary stage with explicit transition criteria, provide a feasible technical pathway for similar projects that require priority construction of working platforms before deep reinforcement.

Authors

Institutions

Publication Details

Journal
Frontiers in Materials
Published
2026-11-18
DOI
https://doi.org/10.3389/fmats.2026.2024114
Primary Topic
Geotechnical Engineering and Soil Stabilization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Mechanism of shallow hard-shell-layer formation for newly-reclaimed dredged silt using vacuum dewatering combined with preloading

Cui Chun-lei, Zeng Si-ping, Yonggang Zhang, Hongliang Tu
1 links
Frontiers in Materials
Geotechnical Engineering and Soil Stabilization
article

Mechanism of shallow hard-shell-layer formation for newly-reclaimed dredged silt using vacuum dewatering combined with preloading

Cui Chun-lei, Zeng Si-ping, Yonggang Zhang, Hongliang Tu
article en

Abstract

Newly-reclaimed dredged silt sites present a critical geotechnical challenge immediately after hydraulic filling. The ground surface remains as fluidized mud, preventing personnel and equipment access, yet conventional treatment methods assume the site is already accessible. This paper proposes a vacuum dewatering combined with preloading (VDCP) method for rapid formation of a shallow hard-shell layer without sand cushions or prolonged drying. A three-dimensional horizontal–vertical drainage network is established, coupling free-water extraction and negative-pressure consolidation. Physical model tests on Xiamen dredged silt (initial water content 281%) and Plaxis 2D numerical simulations are conducted to investigate the reinforcement mechanisms during the hard-shell formation stage. After 1,188 h of vacuum extraction, the average water content of the shallow soil decreases to 58%, the void ratio reduces from 7.53 to 1.49, and the ultimate bearing capacity increases from near zero to over 40 kPa, meeting the requirements for personnel and light machinery access. Numerical comparisons demonstrate that the three-dimensional drainage system achieves approximately 61.0% excess pore water pressure dissipation within 1,200 h, compared with 22.4% for horizontal-only and 18.3% for vertical-only drainage, confirming the synergistic effect of combined drainage channels, although these ratios are semi-quantitative. A consolidation coupling effect between vacuum and surcharge is observed; however, surcharge should be applied only after the soil has gained sufficient shear strength. The VDCP method and the proposed phased treatment framework, which designates shallow hard-shell formation as an independent preliminary stage with explicit transition criteria, provide a feasible technical pathway for similar projects that require priority construction of working platforms before deep reinforcement.

Frontiers in MaterialsVol. 13
Chinese Academy of Sciences (CN), Zhejiang Shuren University (CN), Institute of Rock and Soil Mechanics (CN), State Key Laboratory of Geomechanics and Geotechnical Engineering (CN)
Clean water and sanitation, Industry, innovation and infrastructure
Geotechnical Engineering and Soil Stabilization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon