Analysis of the Causes of Delays in Cement Delivery at CP Tuban Using the FTA and FMEA Methods at PT XYZ

On-time delivery is a key indicator for maintaining smooth supply chain operations and ensuring customer satisfaction in cement distribution. However, between May and August 2026, cement shipments from CP Tuban experienced 3,420 instances of delay, primarily due to issues related to inventory levels, the goods release process, and excessive parking duration. This study aims to identify the causes of these delivery delays, determine which causes require the most urgent attention, and propose improvements. The Fault Tree Analysis (FTA) method is used to map the causes of delays into a hierarchical structure, while Failure Mode and Effects Analysis (FMEA) is employed to assess the risk of each cause via a Risk Priority Number (RPN). Data were collected through interviews with the General Manager and the Head of the Logistic Control Tower team, questionnaires assessing severity, occurrence, and detection (completed by two respondents), as well as On-Time Delivery (OTD) data and Root Cause Analysis (RCA). The FTA identified 14 basic events categorized under warehouse constraints, driver-related issues, and accidents all linked via OR gates, meaning each can directly lead to a delay. The FMEA yielded RPN values ​​ranging from 48 to 448, with the four highest-priority issues being: failure to adhere to maintenance schedules (448), failure to complete equipment checklists (392), drivers neglecting to provide confirmation via the application (378), and drivers taking excessively long breaks (324). Improvements are proposed using the 5W+1H framework, including automated maintenance schedule reminders, mandatory digital equipment checklists to be completed prior to departure, automated confirmation prompts within the driver application, and automated notifications combined with the tracking of driver parking duration. The combination of FTA and FMEA not only identifies the causes of delays but also determines which causes should be prioritized for improvement.

Authors

Institutions

Publication Details

Journal
International Journal Of Science Technology & Management
Published
2026-11-18
DOI
https://doi.org/10.46729/ijstm.v7i6.1526
Primary Topic
Business Logistics and Inventory Control
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Analysis of the Causes of Delays in Cement Delivery at CP Tuban Using the FTA and FMEA Methods at PT XYZ

Efta Dhartikasari Priyana, Purwanto, Fahrizal Dwi Prasetya
4 links
International Journal Of Science Technology & Management
Business Logistics and Inventory Control
article

Analysis of the Causes of Delays in Cement Delivery at CP Tuban Using the FTA and FMEA Methods at PT XYZ

Efta Dhartikasari Priyana, Purwanto, Fahrizal Dwi Prasetya
article en

Abstract

On-time delivery is a key indicator for maintaining smooth supply chain operations and ensuring customer satisfaction in cement distribution. However, between May and August 2026, cement shipments from CP Tuban experienced 3,420 instances of delay, primarily due to issues related to inventory levels, the goods release process, and excessive parking duration. This study aims to identify the causes of these delivery delays, determine which causes require the most urgent attention, and propose improvements. The Fault Tree Analysis (FTA) method is used to map the causes of delays into a hierarchical structure, while Failure Mode and Effects Analysis (FMEA) is employed to assess the risk of each cause via a Risk Priority Number (RPN). Data were collected through interviews with the General Manager and the Head of the Logistic Control Tower team, questionnaires assessing severity, occurrence, and detection (completed by two respondents), as well as On-Time Delivery (OTD) data and Root Cause Analysis (RCA). The FTA identified 14 basic events categorized under warehouse constraints, driver-related issues, and accidents all linked via OR gates, meaning each can directly lead to a delay. The FMEA yielded RPN values ​​ranging from 48 to 448, with the four highest-priority issues being: failure to adhere to maintenance schedules (448), failure to complete equipment checklists (392), drivers neglecting to provide confirmation via the application (378), and drivers taking excessively long breaks (324). Improvements are proposed using the 5W+1H framework, including automated maintenance schedule reminders, mandatory digital equipment checklists to be completed prior to departure, automated confirmation prompts within the driver application, and automated notifications combined with the tracking of driver parking duration. The combination of FTA and FMEA not only identifies the causes of delays but also determines which causes should be prioritized for improvement.

International Journal Of Science Technology & ManagementVol. 7(6)
Universitas Muhammadiyah Gresik (ID), Universitas Gresik (ID)
Industry, innovation and infrastructure
Business Logistics and Inventory Control
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon