Effect of Project Planning Practices on the Performance of Government Hydropower Project in Rwanda: A Case of Nyabarongo II Hydropower Plant Project

Despite Rwanda's strong policy commitment to infrastructure-led development and its regional reputation for disciplined public investment governance, government-backed projects consistently face implementation and operational challenges that are traceable to fragmented upstream planning practices.This study examined the effect of project planning practices on the performance of the Nyabarongo II Hydropower Plant Project in Rwanda.Despite national infrastructure investments, hydropower projects face delays and cost overruns linked to planning deficits.Anchored in Project Management and Systems Theories, a descriptive-explanatory quantitative design was employed.Using Yamane's formula, 176 participants were sampled from a population of 314, achieving a 96.3% response rate (n = 170).Data were collected using structured questionnaires.The instrument demonstrated high reliability, with Cronbach's alpha values ranging from 0.829 to 0.947.Quantitative data were analyzed using SPSS v27 through descriptive statistics, Pearson correlation, and multiple regression.Results indicated that scope planning (β = .755,p < .001),time planning (β = .132,p = .020),and risk planning (β = .152,p = .011)significantly and positively influenced project performance.However, cost planning was insignificant in the combined model (β = -.083,p = .055).The integrated model explained 84.8% of the variance in project performance (R² = .848,F = 229.343,p < .001).The study concludes that integrated scope, time, and risk planning are critical for government hydropower success.It recommends strengthening scope validation, realistic scheduling, and proactive risk registers, while integrating cost planning with other dimensions.

Publication Details

Journal
Journal of Research Innovation and Implications in Education
Published
2026-11-18
DOI
https://doi.org/10.59765/ksw2y9
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Effect of Project Planning Practices on the Performance of Government Hydropower Project in Rwanda: A Case of Nyabarongo II Hydropower Plant Project

4 links
Journal of Research Innovation and Implications in Education
Construction Project Management and Performance
article

Effect of Project Planning Practices on the Performance of Government Hydropower Project in Rwanda: A Case of Nyabarongo II Hydropower Plant Project

article en

Abstract

Despite Rwanda's strong policy commitment to infrastructure-led development and its regional reputation for disciplined public investment governance, government-backed projects consistently face implementation and operational challenges that are traceable to fragmented upstream planning practices.This study examined the effect of project planning practices on the performance of the Nyabarongo II Hydropower Plant Project in Rwanda.Despite national infrastructure investments, hydropower projects face delays and cost overruns linked to planning deficits.Anchored in Project Management and Systems Theories, a descriptive-explanatory quantitative design was employed.Using Yamane's formula, 176 participants were sampled from a population of 314, achieving a 96.3% response rate (n = 170).Data were collected using structured questionnaires.The instrument demonstrated high reliability, with Cronbach's alpha values ranging from 0.829 to 0.947.Quantitative data were analyzed using SPSS v27 through descriptive statistics, Pearson correlation, and multiple regression.Results indicated that scope planning (β = .755,p < .001),time planning (β = .132,p = .020),and risk planning (β = .152,p = .011)significantly and positively influenced project performance.However, cost planning was insignificant in the combined model (β = -.083,p = .055).The integrated model explained 84.8% of the variance in project performance (R² = .848,F = 229.343,p < .001).The study concludes that integrated scope, time, and risk planning are critical for government hydropower success.It recommends strengthening scope validation, realistic scheduling, and proactive risk registers, while integrating cost planning with other dimensions.

Journal of Research Innovation and Implications in Education
Industry, innovation and infrastructure
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon