Multiobjective optimization model for project time and cost management under multiperiod financial constraints

Abstract This study introduces a novel mathematical formulation for the multi-mode project scheduling problem that concurrently optimizes project duration and total direct cost under strict periodic budget constraints. To navigate the highly non-linear, combinatorial decision space inherent in this framework, a multi-objective evolutionary metaheuristic is developed to systematically map the non-dominated Pareto-optimal frontier. The practical efficacy and algorithmic accuracy of this proposed methodology are validated using an empirical case study centered on a flooring installation network within a large-scale government building infrastructure project. To establish a rigorous validation benchmark, the frontier solutions derived from the genetic metaheuristic were evaluated against an exact global optimization baseline generated via the GAMS (General Algebraic Modeling System). The multi-objective optimization model successfully identifies a robust baseline Pareto-optimal project duration of 64 working days. Comprehensive sensitivity analysis indicates that while an increase in capital allocation generally compresses project timelines by facilitating resource-intensive execution modes, this relationship is bound by distinct financial and physical plateaus. Additional schedule compression to 63 and 62 working days is conditionally achievable only when periodic financial boundaries are extended to their maximum upper limits. At this threshold, exact mathematical validation uncovers the absolute physical limit of the construction network, beyond which further budget injections yield diminishing returns regarding duration reduction. Crucially, the trade-off configurations generated by the non-dominated sorting genetic algorithm display a strong convergence profile, aligning closely with the global optima produced by the exact GAMS solver. This mathematical agreement demonstrates the performance, precision, and structural reliability of the calibrated metaheuristic when navigating complex project networks under multi-period financial constraints. Ultimately, this framework provides project managers and public procurement authorities with a highly practical decision-support tool capable of balancing tight delivery timelines and implementation expenditures within predefined, real-world fiscal boundaries.

Authors

Institutions

Publication Details

Journal
Discover Civil Engineering
Published
2026-11-17
DOI
https://doi.org/10.1007/s44290-026-00678-6
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Multiobjective optimization model for project time and cost management under multiperiod financial constraints

Nima Amani
1 links
Discover Civil Engineering
Resource-Constrained Project Scheduling
article

Multiobjective optimization model for project time and cost management under multiperiod financial constraints

Nima Amani
article en

Abstract

Abstract This study introduces a novel mathematical formulation for the multi-mode project scheduling problem that concurrently optimizes project duration and total direct cost under strict periodic budget constraints. To navigate the highly non-linear, combinatorial decision space inherent in this framework, a multi-objective evolutionary metaheuristic is developed to systematically map the non-dominated Pareto-optimal frontier. The practical efficacy and algorithmic accuracy of this proposed methodology are validated using an empirical case study centered on a flooring installation network within a large-scale government building infrastructure project. To establish a rigorous validation benchmark, the frontier solutions derived from the genetic metaheuristic were evaluated against an exact global optimization baseline generated via the GAMS (General Algebraic Modeling System). The multi-objective optimization model successfully identifies a robust baseline Pareto-optimal project duration of 64 working days. Comprehensive sensitivity analysis indicates that while an increase in capital allocation generally compresses project timelines by facilitating resource-intensive execution modes, this relationship is bound by distinct financial and physical plateaus. Additional schedule compression to 63 and 62 working days is conditionally achievable only when periodic financial boundaries are extended to their maximum upper limits. At this threshold, exact mathematical validation uncovers the absolute physical limit of the construction network, beyond which further budget injections yield diminishing returns regarding duration reduction. Crucially, the trade-off configurations generated by the non-dominated sorting genetic algorithm display a strong convergence profile, aligning closely with the global optima produced by the exact GAMS solver. This mathematical agreement demonstrates the performance, precision, and structural reliability of the calibrated metaheuristic when navigating complex project networks under multi-period financial constraints. Ultimately, this framework provides project managers and public procurement authorities with a highly practical decision-support tool capable of balancing tight delivery timelines and implementation expenditures within predefined, real-world fiscal boundaries.

Discover Civil EngineeringVol. 3(1)
Islamic Azad University of Chalous (IR)
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon