Binding but Not Final: The Enforceability of Dispute Board Decisions in Indian Construction Arbitration

Dispute boards are now a standard feature of major construction contracts, and their value rests on one idea: a board’s decision binds the parties immediately, even though it is not final, so that cash flow and progress are not held hostage to a full arbitration. That idea works only if a non-compliant party can be compelled to comply quickly. This paper asks whether Indian law supplies that compulsion. Using a doctrinal and comparative method, it analyses the enforcement gap in the 1999 FIDIC conditions, the repair attempted in the 2017 editions, the Singapore litigation known as Persero, the English decision in Peterborough, and Indian authority on dispute review boards and pre-arbitral requirements. It reaches three findings. First, Indian courts have so far treated boards mainly as a mandatory gateway to arbitration and, in the decisions examined, have not squarely decided whether a binding but non-final decision can be enforced in isolation. Second, the Arbitration and Conciliation Act, 1996 already contains the tools that Singapore used to close the gap, namely interim awards and interim measures, so legislative amendment is not strictly needed. Third, many public-sector contracts, where most Indian construction disputes arise, use boards whose output is a recommendation and not a binding decision, and recent procurement policy favouring mediation over arbitration for large contracts adds uncertainty about the final forum. The paper proposes a three-part framework: an express compliance-and-referral clause in the contract, deliberate use of interim awards by tribunals, and alignment of procurement guidelines with board practice. It concludes that India can enforce board decisions without new legislation, but only if contracts and tribunals are deliberate about doing so.

Authors

Institutions

Publication Details

Journal
International Journal of Law Management & Humanities
Published
2026-11-16
DOI
https://doi.org/10.63108/ijlmh.13221
Primary Topic
International Arbitration and Investment Law
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Binding but Not Final: The Enforceability of Dispute Board Decisions in Indian Construction Arbitration

Aseem Chandra Paliwal, Grishma Brahmbhatt
International Journal of Law Management & Humanities
International Arbitration and Investment Law
article

Binding but Not Final: The Enforceability of Dispute Board Decisions in Indian Construction Arbitration

Aseem Chandra Paliwal, Grishma Brahmbhatt
article en

Abstract

Dispute boards are now a standard feature of major construction contracts, and their value rests on one idea: a board’s decision binds the parties immediately, even though it is not final, so that cash flow and progress are not held hostage to a full arbitration. That idea works only if a non-compliant party can be compelled to comply quickly. This paper asks whether Indian law supplies that compulsion. Using a doctrinal and comparative method, it analyses the enforcement gap in the 1999 FIDIC conditions, the repair attempted in the 2017 editions, the Singapore litigation known as Persero, the English decision in Peterborough, and Indian authority on dispute review boards and pre-arbitral requirements. It reaches three findings. First, Indian courts have so far treated boards mainly as a mandatory gateway to arbitration and, in the decisions examined, have not squarely decided whether a binding but non-final decision can be enforced in isolation. Second, the Arbitration and Conciliation Act, 1996 already contains the tools that Singapore used to close the gap, namely interim awards and interim measures, so legislative amendment is not strictly needed. Third, many public-sector contracts, where most Indian construction disputes arise, use boards whose output is a recommendation and not a binding decision, and recent procurement policy favouring mediation over arbitration for large contracts adds uncertainty about the final forum. The paper proposes a three-part framework: an express compliance-and-referral clause in the contract, deliberate use of interim awards by tribunals, and alignment of procurement guidelines with board practice. It concludes that India can enforce board decisions without new legislation, but only if contracts and tribunals are deliberate about doing so.

International Journal of Law Management & HumanitiesVol. 9(VI)
Gujarat National Law University (IN), Karnavati University (IN)
Peace, justice, and strong institutions
International Arbitration and Investment Law
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon