At its deepest, the 12 August eclipse cost Spain about 4.2 GW of solar output

Grid operators spent days bracing for the eclipse. It came, smaller and shorter than the biggest forecasts. Measured against clear days, Spain was down about 4.2 GW at the deepest point and Germany-Luxembourg about 1.9 GW. Most of it happened within a single hour of early evening. This record holds the technical note as a PDF and the summary tables behind its table and two figures: shortfall by zone and quarter-hour, peak shortfall and energy by zone, forecasts against outturn, daily solar energy and the clear days used for each baseline. The original article is at https://sdafintech.com/articles/2026/august-eclipse-solar-output. The full ENTSO-E series are not republished. Source data: ENTSO-E Transparency Platform (https://transparency.entsoe.eu/): actual generation per production type (solar, document A75) and day-ahead and intraday solar forecasts (A69), 2 to 22 August 2026. Modified: for each zone we built a clear-day baseline per quarter-hour, subtracted actual output and summarised the shortfall by zone, time slot and day. Retrieved 14 September 2026. Not endorsed by ENTSO-E. Authored by Sustainable Digital Assets Inc., the issuer of SDA Token. Informational; not investment advice.

Authors

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2026-11-16
DOI
https://doi.org/10.5281/zenodo.24290239
Primary Topic
Solar Radiation and Photovoltaics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

At its deepest, the 12 August eclipse cost Spain about 4.2 GW of solar output

Mikko Rautiainen
1 links
Zenodo (CERN European Organization for Nuclear Research)
Solar Radiation and Photovoltaics
article

At its deepest, the 12 August eclipse cost Spain about 4.2 GW of solar output

Mikko Rautiainen
article en

Abstract

Grid operators spent days bracing for the eclipse. It came, smaller and shorter than the biggest forecasts. Measured against clear days, Spain was down about 4.2 GW at the deepest point and Germany-Luxembourg about 1.9 GW. Most of it happened within a single hour of early evening. This record holds the technical note as a PDF and the summary tables behind its table and two figures: shortfall by zone and quarter-hour, peak shortfall and energy by zone, forecasts against outturn, daily solar energy and the clear days used for each baseline. The original article is at https://sdafintech.com/articles/2026/august-eclipse-solar-output. The full ENTSO-E series are not republished. Source data: ENTSO-E Transparency Platform (https://transparency.entsoe.eu/): actual generation per production type (solar, document A75) and day-ahead and intraday solar forecasts (A69), 2 to 22 August 2026. Modified: for each zone we built a clear-day baseline per quarter-hour, subtracted actual output and summarised the shortfall by zone, time slot and day. Retrieved 14 September 2026. Not endorsed by ENTSO-E. Authored by Sustainable Digital Assets Inc., the issuer of SDA Token. Informational; not investment advice.

Zenodo (CERN European Organization for Nuclear Research)
Climate action, Affordable and clean energy, Industry, innovation and infrastructure
Solar Radiation and Photovoltaics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon