Break‐Even Conditions for HTS‐HVDC in Constrained High‐Capacity Renewable‐Energy Transmission Corridors

ABSTRACT Constrained transmission corridors motivate comparison of high‐temperature superconducting high‐voltage direct‐current (HTS‐HVDC) with conventional VSC‐HVDC under a common receiving‐end service and contingency requirement. This study links three questions: how transmission ratings determine installed reserve, how much additional conventional corridor capital is required for parity and what conductor procurement price permits parity. The calculation purchases complete cable, converter and cooling inventories for independent modules and evaluates lifecycle expenditure and delivered energy. A 2‐GW conventional reference is compared with 2‐, 3‐, 4‐ and 5‐GW HTS planning modules using a common converter–cost relationship. At 2.1 GW receiving‐end power and 500 km, the additional conventional capital required for parity is approximately USD 0.80 billion for equal‐2‐GW modules and USD 1.39 billion for 5‐GW HTS modules. Fewer HTS assemblies can therefore coincide with a higher cost of installed reserve. Conductor‐price thresholds depend on that architecture and the assumed additional‐corridor capital; three heat‐ingress scenarios show their thermal sensitivity. Reliability and input uncertainty qualify these conditions rather than establish commercial feasibility. The calculations use published component correlations and explicit author cost and reliability scenarios. Historical project comparisons do not validate the conventional coefficients, and conductor‐current evidence does not qualify a complete 5‐GW cable system. The outputs are architecture‐specific conditions for further engineering and project appraisal, not estimates of demonstrated avoided corridor expenditure.

Authors

Institutions

Publication Details

Journal
Energy Science & Engineering
Published
2026-11-16
DOI
https://doi.org/10.1002/ese3.70701
Primary Topic
HVDC Systems and Fault Protection
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Break‐Even Conditions for HTS‐HVDC in Constrained High‐Capacity Renewable‐Energy Transmission Corridors

Saman Asghari Gorji, Alireza Ganjovi
1 links
Energy Science & Engineering
HVDC Systems and Fault Protection
article

Break‐Even Conditions for HTS‐HVDC in Constrained High‐Capacity Renewable‐Energy Transmission Corridors

Saman Asghari Gorji, Alireza Ganjovi
article en

Abstract

ABSTRACT Constrained transmission corridors motivate comparison of high‐temperature superconducting high‐voltage direct‐current (HTS‐HVDC) with conventional VSC‐HVDC under a common receiving‐end service and contingency requirement. This study links three questions: how transmission ratings determine installed reserve, how much additional conventional corridor capital is required for parity and what conductor procurement price permits parity. The calculation purchases complete cable, converter and cooling inventories for independent modules and evaluates lifecycle expenditure and delivered energy. A 2‐GW conventional reference is compared with 2‐, 3‐, 4‐ and 5‐GW HTS planning modules using a common converter–cost relationship. At 2.1 GW receiving‐end power and 500 km, the additional conventional capital required for parity is approximately USD 0.80 billion for equal‐2‐GW modules and USD 1.39 billion for 5‐GW HTS modules. Fewer HTS assemblies can therefore coincide with a higher cost of installed reserve. Conductor‐price thresholds depend on that architecture and the assumed additional‐corridor capital; three heat‐ingress scenarios show their thermal sensitivity. Reliability and input uncertainty qualify these conditions rather than establish commercial feasibility. The calculations use published component correlations and explicit author cost and reliability scenarios. Historical project comparisons do not validate the conventional coefficients, and conductor‐current evidence does not qualify a complete 5‐GW cable system. The outputs are architecture‐specific conditions for further engineering and project appraisal, not estimates of demonstrated avoided corridor expenditure.

Energy Science & Engineering
Deakin University (AU)
Industry, innovation and infrastructure, Affordable and clean energy
HVDC Systems and Fault Protection
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon