Francis Reaction Turbine for a Mid-Head River Dam: Runner, Draft Tube and Cavitation Budgets for an 8.5 Megawatt Plant

A vertical Francis turbine at a mid-head river dam is designed here from first budgets upward. Its operating principle: water enters a spiral case under pressure, passes adjustable guide vanes that set both flow and swirl, and gives up energy across a fully submerged runner, with a draft tube recovering much of the leaving kinetic energy. At a net head of 80.8 metres and 12.0 cubic metres per second, the runner of 1.82 metres diameter delivers 8,490 kilowatts net; the plant cavitation number is 0.094 against a critical value of 0.056, a margin of 1.7. The cavitation budget is the centre of this design: the runner setting below tailwater is chosen from the computed plant cavitation number, not from habit, and the draft tube recovery fraction is carried as an explicit term so its contribution to output can be audited. Part-load swirl instability is treated as an operating restriction with a stated excluded band rather than as a surprise. Every dimension and rating traces back to budgets for head, discharge, runner efficiency and cavitation, plus an energy-storage budget where the plant stores water for later use, all evaluated by the deposited program from its declared inputs. This is a civilian power design, computed and simulated rather than measured, with no weapon or targeting application anywhere in it.

Authors

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2026-11-15
DOI
https://doi.org/10.5281/zenodo.24242874
Primary Topic
Cavitation Phenomena in Pumps
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Francis Reaction Turbine for a Mid-Head River Dam: Runner, Draft Tube and Cavitation Budgets for an 8.5 Megawatt Plant

William Alexander Aldred
Zenodo (CERN European Organization for Nuclear Research)
Cavitation Phenomena in Pumps
article

Francis Reaction Turbine for a Mid-Head River Dam: Runner, Draft Tube and Cavitation Budgets for an 8.5 Megawatt Plant

William Alexander Aldred
article en

Abstract

A vertical Francis turbine at a mid-head river dam is designed here from first budgets upward. Its operating principle: water enters a spiral case under pressure, passes adjustable guide vanes that set both flow and swirl, and gives up energy across a fully submerged runner, with a draft tube recovering much of the leaving kinetic energy. At a net head of 80.8 metres and 12.0 cubic metres per second, the runner of 1.82 metres diameter delivers 8,490 kilowatts net; the plant cavitation number is 0.094 against a critical value of 0.056, a margin of 1.7. The cavitation budget is the centre of this design: the runner setting below tailwater is chosen from the computed plant cavitation number, not from habit, and the draft tube recovery fraction is carried as an explicit term so its contribution to output can be audited. Part-load swirl instability is treated as an operating restriction with a stated excluded band rather than as a surprise. Every dimension and rating traces back to budgets for head, discharge, runner efficiency and cavitation, plus an energy-storage budget where the plant stores water for later use, all evaluated by the deposited program from its declared inputs. This is a civilian power design, computed and simulated rather than measured, with no weapon or targeting application anywhere in it.

Zenodo (CERN European Organization for Nuclear Research)
Cavitation Phenomena in Pumps
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon