Ground-Induced Currents and Transformer Half-Cycle Saturation in the Hydro-Quebec Collapse of March 1989

For the Hydro-Quebec transmission system on 13 March 1989: a 735-kilovolt transmission system carrying power from James Bay to load centres hundreds of kilometres south, in which storm-driven quasi-direct currents entered transformer neutrals, drove cores into half-cycle saturation, generated harmonics and reactive-power demand, tripped static compensators, and collapsed the system in about ninety seconds, leaving six million people without power for up to nine hours. A geoelectric field integrated along a line drives a quasi-direct current through the loop formed by the line, transformer windings and the Earth; when that direct current offsets the core flux of a transformer, the core saturates on one half of each alternating cycle, drawing large magnetising current spikes and injecting harmonics. First values are geoelectric field V per km = 4; effective line length km = 250; driving voltage V = 1000; loop resistance ohm = 8; gic per phase A = 125; gic three phase total A = 375. Each quantity, for Hydro Quebec saturation currents and compensator trips, is derived, for Hydro Quebec saturation currents and compensator trips, from stated inputs, for Hydro Quebec saturation currents and compensator trips, across the deposited computation, for Hydro Quebec saturation currents and compensator trips, and set, for Hydro Quebec saturation currents and compensator trips, beside published values, for Hydro Quebec saturation currents and compensator trips, so the accord, for Hydro Quebec saturation currents and compensator trips, in network ground-induced current and saturation, for Hydro Quebec saturation currents and compensator trips, can be audited, for Hydro Quebec saturation currents and compensator trips, number by number, for Hydro Quebec saturation currents and compensator trips.

Authors

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2026-11-15
DOI
https://doi.org/10.5281/zenodo.24251721
Primary Topic
Power System Optimization and Stability
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Ground-Induced Currents and Transformer Half-Cycle Saturation in the Hydro-Quebec Collapse of March 1989

William Alexander Aldred
Zenodo (CERN European Organization for Nuclear Research)
Power System Optimization and Stability
article

Ground-Induced Currents and Transformer Half-Cycle Saturation in the Hydro-Quebec Collapse of March 1989

William Alexander Aldred
article en

Abstract

For the Hydro-Quebec transmission system on 13 March 1989: a 735-kilovolt transmission system carrying power from James Bay to load centres hundreds of kilometres south, in which storm-driven quasi-direct currents entered transformer neutrals, drove cores into half-cycle saturation, generated harmonics and reactive-power demand, tripped static compensators, and collapsed the system in about ninety seconds, leaving six million people without power for up to nine hours. A geoelectric field integrated along a line drives a quasi-direct current through the loop formed by the line, transformer windings and the Earth; when that direct current offsets the core flux of a transformer, the core saturates on one half of each alternating cycle, drawing large magnetising current spikes and injecting harmonics. First values are geoelectric field V per km = 4; effective line length km = 250; driving voltage V = 1000; loop resistance ohm = 8; gic per phase A = 125; gic three phase total A = 375. Each quantity, for Hydro Quebec saturation currents and compensator trips, is derived, for Hydro Quebec saturation currents and compensator trips, from stated inputs, for Hydro Quebec saturation currents and compensator trips, across the deposited computation, for Hydro Quebec saturation currents and compensator trips, and set, for Hydro Quebec saturation currents and compensator trips, beside published values, for Hydro Quebec saturation currents and compensator trips, so the accord, for Hydro Quebec saturation currents and compensator trips, in network ground-induced current and saturation, for Hydro Quebec saturation currents and compensator trips, can be audited, for Hydro Quebec saturation currents and compensator trips, number by number, for Hydro Quebec saturation currents and compensator trips.

Zenodo (CERN European Organization for Nuclear Research)
Power System Optimization and Stability
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon