COMPARATIVE ANALYSIS OF QUANTITY TAKE OFF CALCULATIONS FOR STRUCTURAL WORK USING BIM AND CONVENTIONAL METHODS
Quantity Take Off (QTO) accuracy is essential for effective material estimation and project cost control, particularly for pilecap structures with complex reinforcement configurations. This study compares the accuracy of reinforcement and concrete quantities, as well as processing time, between Building Information Modeling (BIM) and conventional QTO methods using three categories of pilecap in the Solo-Yogyakarta-NYIA Kulon Progo Toll Road Project, Package 2.2B Trihanggo-Junction Sleman (STA 54+635 to STA 57+839). The BIM based method employed Autodesk Revit for three dimensional modeling and automatic quantity extraction, while the conventional method used AutoCAD and Microsoft Excel for manual calculations. The results revealed minimal differences in reinforcement (0.677%) and concrete volume (0.014%), indicating a very high level of agreement between both methods. However, the BIM based method required substantially longer processing time due to the additional three dimensional modeling process. These findings indicate that the primary distinction between the two methods lies in the QTO preparation process rather than the resulting material quantities.
Authors
- Lintang Enggartiasto (ORCID: https://orcid.org/0009-0008-1836-3834)
- Agung Kristiawan (ORCID: https://orcid.org/0009-0000-3281-5333)
- Ahmad Qohhar
- Pramananda Nayaka Wijaya
Publication Details
- Journal
- International Journal of Sustainable Building Infrastructure and Environment (IJOSBIE)
- Published
- 2026-11-14
- DOI
- https://doi.org/10.26877/ijosbie.v7i2.1183
- Primary Topic
- BIM and Construction Integration
- Type
- article
- Field-Weighted Citation Impact
- 0.00