ANALYSIS OF TIME WASTE IN READY-MIX PRODUCTION USING THE LEAN MANUFACTURING APPROACH WITH THE VALUE STREAM MAPPING (VSM) METHOD IN THE CONCRETE MANUFACTURING INDUSTRY

This study aims to identify waste and reduce time waste in the ready-mix concrete production process through proposed improvements at PT Bosowa Beton Indonesia by applying a quantitative descriptive approach, with data collected through observation, interviews, and documentation and analyzed using Process Activity Mapping (PAM), Current State Mapping (CSM), waste identification, 5W+1H analysis, and Future State Mapping (FSM), with the results showing that waiting was the dominant form of waste, while the initial condition had a lead time of 40.44 minutes consisting of 10.81 minutes of Value Added (VA), 12.42 minutes of Non-Value Added (NVA), and 17.21 minutes of Necessary Non-Value Added (NNVA), which was reduced to 30.65 minutes after implementing the proposed improvements, with NVA activities successfully eliminated, demonstrating that the application of Lean Manufacturing using the Value Stream Mapping method is effective in identifying waste, reducing production time, and improving the efficiency of the ready-mix concrete production process.

Authors

Publication Details

Journal
Journal of Industrial Engineering Management
Published
2026-11-12
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

ANALYSIS OF TIME WASTE IN READY-MIX PRODUCTION USING THE LEAN MANUFACTURING APPROACH WITH THE VALUE STREAM MAPPING (VSM) METHOD IN THE CONCRETE MANUFACTURING INDUSTRY

Rahmaniah Malik, Yan Herdianzah, Alifah Dwi Putri
Journal of Industrial Engineering Management
Management and Optimization Techniques
article

ANALYSIS OF TIME WASTE IN READY-MIX PRODUCTION USING THE LEAN MANUFACTURING APPROACH WITH THE VALUE STREAM MAPPING (VSM) METHOD IN THE CONCRETE MANUFACTURING INDUSTRY

Rahmaniah Malik, Yan Herdianzah, Alifah Dwi Putri
article en

Abstract

This study aims to identify waste and reduce time waste in the ready-mix concrete production process through proposed improvements at PT Bosowa Beton Indonesia by applying a quantitative descriptive approach, with data collected through observation, interviews, and documentation and analyzed using Process Activity Mapping (PAM), Current State Mapping (CSM), waste identification, 5W+1H analysis, and Future State Mapping (FSM), with the results showing that waiting was the dominant form of waste, while the initial condition had a lead time of 40.44 minutes consisting of 10.81 minutes of Value Added (VA), 12.42 minutes of Non-Value Added (NVA), and 17.21 minutes of Necessary Non-Value Added (NNVA), which was reduced to 30.65 minutes after implementing the proposed improvements, with NVA activities successfully eliminated, demonstrating that the application of Lean Manufacturing using the Value Stream Mapping method is effective in identifying waste, reducing production time, and improving the efficiency of the ready-mix concrete production process.

Journal of Industrial Engineering Management
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon