Partial Cost Information and Empirical Contingency in Building Retrofit Cost Prediction
This study retrospectively evaluated partial cost information and empirical contingency in an archived extract of public-building retrofits. The primary reporting sample comprised 246 records, with all 250 retained for sensitivity analysis. Adding four recorded component costs reduced total-cost mean absolute percentage error (MAPE) from 23.35% to 17.30% for genetic-algorithm-weighted case-based reasoning and from 23.05% to 14.68% for Extra Trees. The primary comparison did not establish a larger improvement for Extra Trees. Predicting the remaining cost and adding the observed subtotal produced 12.72% total-cost MAPE, but remaining-cost-weighted absolute percentage error was 19.28% and remaining-cost MAPE was 29.42%. The paired target-route difference also remained uncertain. Additional nested selection across 14 family-target routes yielded 12.64% total-cost MAPE within the same archive. The historical project-level 90th-percentile (P90) allowance was 35.47%; separate training/calibration/evaluation splits achieved 76–98% coverage with empirical P90 allowances calibrated on disjoint records. For the largest-area holdout, remaining-cost weighted error reached 46.74%, and the 35.47% historical allowance covered only 62% of cases. The selected extract differed from the other records in our 419-record research archive. Field timing and project dates were unavailable. The results support an evaluation framework, not demonstrated early-stage forecasting accuracy or a transferable contingency rate.
Authors
- Jongmyeong Kim (ORCID: https://orcid.org/0009-0001-8133-6942)
- Nahyun Kwon (ORCID: https://orcid.org/0000-0001-9965-9611)
- Hyosoo Moon (ORCID: https://orcid.org/0000-0001-6555-3181)
- Yonghan Ahn (ORCID: https://orcid.org/0000-0002-5542-7314)
- Sojin Park (ORCID: https://orcid.org/0000-0003-2984-017X)
Institutions
- North Carolina Agricultural and Technical State University (US)
- Hanyang University (KR)
Publication Details
- Journal
- Buildings
- Published
- 2026-11-13
- DOI
- https://doi.org/10.3390/buildings16224530
- Primary Topic
- Construction Project Management and Performance
- Type
- article
- Field-Weighted Citation Impact
- 0.00