Topology-Aware Feasibility Assessment and Coordinated Setting of Transformer Primary and Backup Protection in Islanded Renewable Power Systems

Islanded microgrid topology and converter current limiting can alter transformer protection currents. We formulate primary and backup coordination as a topology-indexed feasible domain. A bridge test identifies source contributions that cross the protected transformer, and a joint model tests differential sensitivity and stability, overcurrent pickup and timing, load security, and device limits. At the selected inputs, four supported bridge states in an eight-entry reference library retain non-empty domains. The weak-GFL case has a narrow backup–pickup interval (0.984–1.042 pu), and its feasibility classification changes across the tested lower-current factors; the high-load case remains empty (1.860 pu load-security lower bound versus 1.326 pu sensitivity upper bound). A seven-bus reference EMT study includes 112 baseline cases, a 1232-case direction/location/resistance scan, and a 288-case coupled-controller scan. The CT stress screen reduces the all-source reference-domain volume from 0.08391 to 0.07059. All numerical results use the declared reference-network and device inputs.

Authors

Institutions

Publication Details

Journal
Energies
Published
2026-11-13
DOI
https://doi.org/10.3390/en19225473
Primary Topic
Power Systems Fault Detection
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Topology-Aware Feasibility Assessment and Coordinated Setting of Transformer Primary and Backup Protection in Islanded Renewable Power Systems

Qi Zhu, Lie Li, Yifan Zhao, Yu Sun
Energies
Power Systems Fault Detection
article

Topology-Aware Feasibility Assessment and Coordinated Setting of Transformer Primary and Backup Protection in Islanded Renewable Power Systems

Qi Zhu, Lie Li, Yifan Zhao, Yu Sun
article en

Abstract

Islanded microgrid topology and converter current limiting can alter transformer protection currents. We formulate primary and backup coordination as a topology-indexed feasible domain. A bridge test identifies source contributions that cross the protected transformer, and a joint model tests differential sensitivity and stability, overcurrent pickup and timing, load security, and device limits. At the selected inputs, four supported bridge states in an eight-entry reference library retain non-empty domains. The weak-GFL case has a narrow backup–pickup interval (0.984–1.042 pu), and its feasibility classification changes across the tested lower-current factors; the high-load case remains empty (1.860 pu load-security lower bound versus 1.326 pu sensitivity upper bound). A seven-bus reference EMT study includes 112 baseline cases, a 1232-case direction/location/resistance scan, and a 288-case coupled-controller scan. The CT stress screen reduces the all-source reference-domain volume from 0.08391 to 0.07059. All numerical results use the declared reference-network and device inputs.

EnergiesVol. 19(22)
State Grid Corporation of China (China) (CN)
State Grid Hubei Electric Power Co
Industry, innovation and infrastructure, Affordable and clean energy
Power Systems Fault Detection
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon