Historical Evaluation of Integrated Project Control Early Warning Indicators in Four United States Transit Capital Projects

Abstract Major U.S. transit capital projects are monitored through cost and schedule measures that may not fully represent change, contractor and construction-interface pressures. This study retrospectively applied the frozen Integrated Project Controls and Risk Forecasting Framework (IPCRF), Version 1.2, to four U.S. transit capital projects with contrasting outcomes: NYCT ADA station improvements, Dulles Corridor Metrorail Phase 2, East Side Access/Grand Central Madison, and the Canarsie Tube/L Project Tunnel Rehabilitation as a favorable-outcome comparator. Twelve selected project-level historical observations were reconstructed from transit-agency and Federal Transit Administration records; Case 4 also contributed eight component-level contingency-stress observations. Additional monthly PMOC records for Dulles and East Side Access were examined in a reporting-period sensitivity analysis. NYCT Finish Slippage moved from Low to Critical after its completion forecast changed but before the original completion target. Dulles retained Low project-level EAC variance while Total Change Exposure remained High, alongside documented contractual milestone failures. East Side Access showed Elevated cost and conditional schedule classifications with access and interface constraints. Canarsie remained Low for Finish Slippage at both historical snapshots; seven component Contingency Stress observations were Low, and one was Watch, with none Elevated or above. Incomplete and uneven records prevented formal six-domain PDRS/FCS scoring. The findings support retrospective indicator-level reconstruction across contrasting outcomes, but do not establish specificity, false-positive performance or prospective predictive validity.

Authors

Institutions

Publication Details

Journal
Research Square
Published
2026-11-12
DOI
https://doi.org/10.21203/rs.3.rs-11283302/v1
Primary Topic
Construction Project Management and Performance
Type
preprint
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
preprint

Historical Evaluation of Integrated Project Control Early Warning Indicators in Four United States Transit Capital Projects

Mohammed Adeyemi Yusuff
Research Square
Construction Project Management and Performance
preprint

Historical Evaluation of Integrated Project Control Early Warning Indicators in Four United States Transit Capital Projects

Mohammed Adeyemi Yusuff
preprint en

Abstract

Abstract Major U.S. transit capital projects are monitored through cost and schedule measures that may not fully represent change, contractor and construction-interface pressures. This study retrospectively applied the frozen Integrated Project Controls and Risk Forecasting Framework (IPCRF), Version 1.2, to four U.S. transit capital projects with contrasting outcomes: NYCT ADA station improvements, Dulles Corridor Metrorail Phase 2, East Side Access/Grand Central Madison, and the Canarsie Tube/L Project Tunnel Rehabilitation as a favorable-outcome comparator. Twelve selected project-level historical observations were reconstructed from transit-agency and Federal Transit Administration records; Case 4 also contributed eight component-level contingency-stress observations. Additional monthly PMOC records for Dulles and East Side Access were examined in a reporting-period sensitivity analysis. NYCT Finish Slippage moved from Low to Critical after its completion forecast changed but before the original completion target. Dulles retained Low project-level EAC variance while Total Change Exposure remained High, alongside documented contractual milestone failures. East Side Access showed Elevated cost and conditional schedule classifications with access and interface constraints. Canarsie remained Low for Finish Slippage at both historical snapshots; seven component Contingency Stress observations were Low, and one was Watch, with none Elevated or above. Incomplete and uneven records prevented formal six-domain PDRS/FCS scoring. The findings support retrospective indicator-level reconstruction across contrasting outcomes, but do not establish specificity, false-positive performance or prospective predictive validity.

Research Square
Northeastern University (US)
Industry, innovation and infrastructure, Sustainable cities and communities
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon