TECHNICAL AND ECONOMIC JUSTIFICATION FOR THE SELECTION OF POWER RESONANCE FILTERS TO IMPROVE THE QUALITY OF POWER SUPPLY AT AN INDUSTRIAL ENTERPRISE

The article presents experimental data on the application of power harmonic filters (PHFs) in a 10 kV network of an industrial enterprise. Based on real-world data, the voltage rise on the 10 kV busbars and the reduction in active power losses were calculated for various switching configurations of the 3rd, 5th, 7th, and 11th harmonic filters. An emergency operating mode is analyzed in which all workshop substations are powered by a single step-down transformer, leading to its overload. Calculations prove that switching on all PHFs ensures a 25.4% transformer unloading and increases the power factor to 0.98. Recommendations for the further modernization of the enterprise's power supply system are provided.

Authors

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2026-11-12
DOI
https://doi.org/10.5281/zenodo.24168969
Primary Topic
Power Quality and Harmonics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

TECHNICAL AND ECONOMIC JUSTIFICATION FOR THE SELECTION OF POWER RESONANCE FILTERS TO IMPROVE THE QUALITY OF POWER SUPPLY AT AN INDUSTRIAL ENTERPRISE

Oleh Kliuiev, Azizov T., Khmelnytskyi E.
Zenodo (CERN European Organization for Nuclear Research)
Power Quality and Harmonics
article

TECHNICAL AND ECONOMIC JUSTIFICATION FOR THE SELECTION OF POWER RESONANCE FILTERS TO IMPROVE THE QUALITY OF POWER SUPPLY AT AN INDUSTRIAL ENTERPRISE

Oleh Kliuiev, Azizov T., Khmelnytskyi E.
article en

Abstract

The article presents experimental data on the application of power harmonic filters (PHFs) in a 10 kV network of an industrial enterprise. Based on real-world data, the voltage rise on the 10 kV busbars and the reduction in active power losses were calculated for various switching configurations of the 3rd, 5th, 7th, and 11th harmonic filters. An emergency operating mode is analyzed in which all workshop substations are powered by a single step-down transformer, leading to its overload. Calculations prove that switching on all PHFs ensures a 25.4% transformer unloading and increases the power factor to 0.98. Recommendations for the further modernization of the enterprise's power supply system are provided.

Zenodo (CERN European Organization for Nuclear Research)
Industry, innovation and infrastructure, Affordable and clean energy
Power Quality and Harmonics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon