Risk Analysis of Delayed Departure of Cement Trucks and Proposed Improvements Using Fishbone Diagram and FMEA

Delays in truck departures can disrupt distribution processes and affect a company’s operational targets. This study aims to identify the causes of cement truck departure delays on the Rembang route at PT Semen Indonesia Logistik and to determine improvement priorities using a Fishbone Diagram and Failure Mode and Effects Analysis (FMEA). A descriptive approach with qualitative and quantitative analysis was applied, using operational departure data for May–July 2026, observations, and assessments by two experts. Of 265 departures, 41 were delayed (15.5%). The Fishbone Diagram grouped the causes into five categories: Man, Method/Environment, Machine, Operational, and Administration. The FMEA showed that receiving warehouse stock constraints (level stock) had the highest Risk Priority Number (RPN) of 392 (S = 8, O = 7, D = 7), followed by prolonged parking time (378) and vehicle breakdowns (RSK) (270). Level stock and prolonged parking were the main improvement priorities, together accounting for 32 of 41 delays (78%), while vehicle breakdowns remain under monitoring because of their highest severity.

Authors

Institutions

Publication Details

Journal
International Journal Of Science Technology & Management
Published
2026-11-11
DOI
https://doi.org/10.46729/ijstm.v7i6.1517
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Risk Analysis of Delayed Departure of Cement Trucks and Proposed Improvements Using Fishbone Diagram and FMEA

Purwanto, Mohamad Lubabul Khadik, Efta Dhartika Priyana
International Journal Of Science Technology & Management
Management and Optimization Techniques
article

Risk Analysis of Delayed Departure of Cement Trucks and Proposed Improvements Using Fishbone Diagram and FMEA

Purwanto, Mohamad Lubabul Khadik, Efta Dhartika Priyana
article en

Abstract

Delays in truck departures can disrupt distribution processes and affect a company’s operational targets. This study aims to identify the causes of cement truck departure delays on the Rembang route at PT Semen Indonesia Logistik and to determine improvement priorities using a Fishbone Diagram and Failure Mode and Effects Analysis (FMEA). A descriptive approach with qualitative and quantitative analysis was applied, using operational departure data for May–July 2026, observations, and assessments by two experts. Of 265 departures, 41 were delayed (15.5%). The Fishbone Diagram grouped the causes into five categories: Man, Method/Environment, Machine, Operational, and Administration. The FMEA showed that receiving warehouse stock constraints (level stock) had the highest Risk Priority Number (RPN) of 392 (S = 8, O = 7, D = 7), followed by prolonged parking time (378) and vehicle breakdowns (RSK) (270). Level stock and prolonged parking were the main improvement priorities, together accounting for 32 of 41 delays (78%), while vehicle breakdowns remain under monitoring because of their highest severity.

International Journal Of Science Technology & ManagementVol. 7(6)
Universitas Muhammadiyah Gresik (ID)
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon