A força vinculante do projeto na empreitada por preço global: limites aos pleitos de aditivos por omissão de planilha e a matriz de riscos na Lei nº 14.133/2021

The global lump-sum contract regime constitutes one of the most widely used contractual execution methods for engineering works and services in the Brazilian public sector. Despite its statutory provision, contract management recurrently suffers from controversies arising from claims filed by contractors alleging omissions or quantitative discrepancies in the reference budget sheet prepared by the Public Administration. Under the aegis of Law No. 14,133/2021 and the consolidated jurisprudence of the Federal Court of Accounts (TCU), the lump-sum contract characterizes an obligation of integral result, in which remuneration is bound to the delivery of the totality of the object defined by the Basic and Executive Design, rendering the budget sheet a mere auxiliary instrument for stage-based schedule measurements. This study analyzes the binding force of graphic designs and descriptive memorials against omissions in reference cost sheets, delimiting the ordinary venture risk and the admissible inaccuracy margin in basic engineering designs. It is demonstrated that quantitative discrepancies inherent to budget estimation do not justify contractual financial amendments, except for unilateral modifications imposed by the Administration or severe and unforeseeable latent defects. As an indispensable mechanism of governance and legal certainty, the Risk Allocation Matrix clause (art. 103 of Law No. 14,133/2021) is analyzed as an instrument that delineates contractual responsibilities and prevents unjust enrichment for both parties.

Authors

Publication Details

Journal
Revista fisio&terapia.
Published
2026-11-11
DOI
https://doi.org/10.69849/x1g0pz77
Primary Topic
Public Procurement and Policy
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

A força vinculante do projeto na empreitada por preço global: limites aos pleitos de aditivos por omissão de planilha e a matriz de riscos na Lei nº 14.133/2021

Matheus Barbosa Martins, Milenne Alves Ferreira, Carla Zanine Arantes, Wendel Serqueira Rocha
Revista fisio&terapia.
Public Procurement and Policy
article

A força vinculante do projeto na empreitada por preço global: limites aos pleitos de aditivos por omissão de planilha e a matriz de riscos na Lei nº 14.133/2021

Matheus Barbosa Martins, Milenne Alves Ferreira, Carla Zanine Arantes, Wendel Serqueira Rocha
article en

Abstract

The global lump-sum contract regime constitutes one of the most widely used contractual execution methods for engineering works and services in the Brazilian public sector. Despite its statutory provision, contract management recurrently suffers from controversies arising from claims filed by contractors alleging omissions or quantitative discrepancies in the reference budget sheet prepared by the Public Administration. Under the aegis of Law No. 14,133/2021 and the consolidated jurisprudence of the Federal Court of Accounts (TCU), the lump-sum contract characterizes an obligation of integral result, in which remuneration is bound to the delivery of the totality of the object defined by the Basic and Executive Design, rendering the budget sheet a mere auxiliary instrument for stage-based schedule measurements. This study analyzes the binding force of graphic designs and descriptive memorials against omissions in reference cost sheets, delimiting the ordinary venture risk and the admissible inaccuracy margin in basic engineering designs. It is demonstrated that quantitative discrepancies inherent to budget estimation do not justify contractual financial amendments, except for unilateral modifications imposed by the Administration or severe and unforeseeable latent defects. As an indispensable mechanism of governance and legal certainty, the Risk Allocation Matrix clause (art. 103 of Law No. 14,133/2021) is analyzed as an instrument that delineates contractual responsibilities and prevents unjust enrichment for both parties.

Revista fisio&terapia.Vol. 30(164)
Public Procurement and Policy
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon