Waste-Heat Recovery for a Small Intermittent Brick Kiln: Air Preheat and Brick Drying, with Costs, Failure Modes and the Cases Where It Is Not Worth Building

SIMULATED, NOT MEASURED. A first-principles design for waste-heat recovery on a small intermittent brick kiln firing 10,000 bricks per batch on a 48-hour schedule. The kiln burns 3,800 kg of firewood per batch and its exhaust carries 33.2% of the fuel energy. A steel-tube recuperator, bypassed during the tar-heavy smoking phase, preheats combustion air to 314 C and recovers 8.93 GJ per batch; the flue gas then dries the next batch of bricks, adding 2.28 GJ of useful heat. Total fuel saving is 19.7%, payback 2.12 years at 70 batches per year and 75 USD per tonne of wood, with tar fouling, acid-dew-point corrosion and draft interference each answered and priced. A thermoelectric tail (702 batches to repay its modules) and a small organic Rankine tail (a loss per batch before capital) are computed and rejected. Recovery is not worth building below about 31 batches per year or below about 36 USD per tonne fuel price. Nothing has been built or hardware-tested; every number comes from the accompanying computation script.

Authors

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2026-11-10
DOI
https://doi.org/10.5281/zenodo.24108730
Citations
1
Primary Topic
Thermodynamic and Exergetic Analyses of Power and Cooling Systems
Type
article
Field-Weighted Citation Impact
1.58
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Waste-Heat Recovery for a Small Intermittent Brick Kiln: Air Preheat and Brick Drying, with Costs, Failure Modes and the Cases Where It Is Not Worth Building

William Alexander Aldred
1 citations
Zenodo (CERN European Organization for Nuclear Research)
Thermodynamic and Exergetic Analyses of Power and Cooling Systems
1.58
article

Waste-Heat Recovery for a Small Intermittent Brick Kiln: Air Preheat and Brick Drying, with Costs, Failure Modes and the Cases Where It Is Not Worth Building

William Alexander Aldred
article en
1 citations

Abstract

SIMULATED, NOT MEASURED. A first-principles design for waste-heat recovery on a small intermittent brick kiln firing 10,000 bricks per batch on a 48-hour schedule. The kiln burns 3,800 kg of firewood per batch and its exhaust carries 33.2% of the fuel energy. A steel-tube recuperator, bypassed during the tar-heavy smoking phase, preheats combustion air to 314 C and recovers 8.93 GJ per batch; the flue gas then dries the next batch of bricks, adding 2.28 GJ of useful heat. Total fuel saving is 19.7%, payback 2.12 years at 70 batches per year and 75 USD per tonne of wood, with tar fouling, acid-dew-point corrosion and draft interference each answered and priced. A thermoelectric tail (702 batches to repay its modules) and a small organic Rankine tail (a loss per batch before capital) are computed and rejected. Recovery is not worth building below about 31 batches per year or below about 36 USD per tonne fuel price. Nothing has been built or hardware-tested; every number comes from the accompanying computation script.

Zenodo (CERN European Organization for Nuclear Research)
Openalex Percentile: Top 25%
Thermodynamic and Exergetic Analyses of Power and Cooling Systems
1.58
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon