TeraWulf Advances $19 Billion Anthropic Lease with Google-Backed Financing and Fluor EPC Agreement in Hawesville, Kentucky
In a November 4, 2026, announcement, the company disclosed that it had signed credit support agreements with Google LLC covering anticipated debt financing and entered into a definitive engineering, procurement, and construction (EPC) agreement with Fluor Enterprises, Inc., for its Justified Data Campus in Hawesville, Kentucky, one of the upcoming data center projects in Kentucky.