Application of cost-time profile as a criterion for optimizing an investment project

Increasing demands for efficient resource allocation and project performance are closely related to balancing economic efficiency and implementation duration. The problem of costtime optimization is a key aspect of investment project planning from the perspective of lean production. Investors and project planners must select appropriate resources, including contractors, equipment, processes, and technology, to ensure efficient project implementation. They are always faced with the need to find a compromise between cost, quality, and time to complete the required activities. The paper analyses a project for building a 50 kW heat and electricity cogeneration plant. Various measures for cost-time optimization of the project are simulated, and their results (project costs, duration, cost-time investment) and consequences are evaluated. The findings show that faster projects offer significant advantages. The article provides important support for decision-making in projects.

Authors

Institutions

Publication Details

Journal
International Journal of Industrial Engineering and Management
Published
2026-11-05
DOI
https://doi.org/10.24867/ijiem-429
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
article

Application of cost-time profile as a criterion for optimizing an investment project

Robert Ojsteršek, Aljaž Javernik, Borut Buchmeister
International Journal of Industrial Engineering and Management
Resource-Constrained Project Scheduling
article

Application of cost-time profile as a criterion for optimizing an investment project

Robert Ojsteršek, Aljaž Javernik, Borut Buchmeister
article en

Abstract

Increasing demands for efficient resource allocation and project performance are closely related to balancing economic efficiency and implementation duration. The problem of costtime optimization is a key aspect of investment project planning from the perspective of lean production. Investors and project planners must select appropriate resources, including contractors, equipment, processes, and technology, to ensure efficient project implementation. They are always faced with the need to find a compromise between cost, quality, and time to complete the required activities. The paper analyses a project for building a 50 kW heat and electricity cogeneration plant. Various measures for cost-time optimization of the project are simulated, and their results (project costs, duration, cost-time investment) and consequences are evaluated. The findings show that faster projects offer significant advantages. The article provides important support for decision-making in projects.

International Journal of Industrial Engineering and ManagementVol. 17(4)
University of Maribor (SI)
Openalex Percentile: Top 13%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon