Delays in Construction Projects: Causes, Effects and Remedies

Construction delays threaten cost certainty, quality, contractual relationships and infrastructure delivery in Nigeria. This study examined the principal causes and effects of construction delays and assessed the remedies used by project stakeholders. A convergent mixed-method design was adopted. Structured questionnaires were distributed to 120 clients, contractors and consultants in Lagos, Abuja, Port Harcourt and Kano; 102 valid responses were returned, representing an 85 per cent response rate. Semi-structured interviews with 15 professionals supplemented the survey. Questionnaire data were analysed with frequencies, percentages and the Relative Importance Index, while interview evidence was organised thematically. Delayed client payments ranked first among the causes of delay (RII = 0.91), followed by poor project planning and scheduling (RII = 0.87), shortage of skilled labour (RII = 0.82), design errors and late revisions (RII = 0.81), and inadequate communication (RII = 0.79). Cost overrun was the most frequently reported effect (90.2 per cent), followed by project abandonment (72.5 per cent) and disputes or litigation (64.7 per cent). Regular progress meetings were the most widely adopted remedy (70.6 per cent), while formal dispute-resolution mechanisms were least reported (42.2 per cent). The findings show that delays arise from interacting financial, managerial, technical and institutional weaknesses. The study recommends enforceable payment schedules, coordinated design review, critical-path monitoring, staged adoption of digital project controls, workforce development and time-bound regulatory approvals. It concludes that sustainable improvement requires shared accountability among clients, contractors, consultants and public regulators.

Authors

Institutions

Publication Details

Journal
IIARD INTERNATIONAL JOURNAL OF GEOGRAPHY AND ENVIRONMENTAL MANAGEMENT
Published
2026-11-04
DOI
https://doi.org/10.56201/ijgem.vol.12.no10.2026.pg167.183
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Delays in Construction Projects: Causes, Effects and Remedies

Reuben A. Okereke
IIARD INTERNATIONAL JOURNAL OF GEOGRAPHY AND ENVIRONMENTAL MANAGEMENT
Construction Project Management and Performance
article

Delays in Construction Projects: Causes, Effects and Remedies

Reuben A. Okereke
article en

Abstract

Construction delays threaten cost certainty, quality, contractual relationships and infrastructure delivery in Nigeria. This study examined the principal causes and effects of construction delays and assessed the remedies used by project stakeholders. A convergent mixed-method design was adopted. Structured questionnaires were distributed to 120 clients, contractors and consultants in Lagos, Abuja, Port Harcourt and Kano; 102 valid responses were returned, representing an 85 per cent response rate. Semi-structured interviews with 15 professionals supplemented the survey. Questionnaire data were analysed with frequencies, percentages and the Relative Importance Index, while interview evidence was organised thematically. Delayed client payments ranked first among the causes of delay (RII = 0.91), followed by poor project planning and scheduling (RII = 0.87), shortage of skilled labour (RII = 0.82), design errors and late revisions (RII = 0.81), and inadequate communication (RII = 0.79). Cost overrun was the most frequently reported effect (90.2 per cent), followed by project abandonment (72.5 per cent) and disputes or litigation (64.7 per cent). Regular progress meetings were the most widely adopted remedy (70.6 per cent), while formal dispute-resolution mechanisms were least reported (42.2 per cent). The findings show that delays arise from interacting financial, managerial, technical and institutional weaknesses. The study recommends enforceable payment schedules, coordinated design review, critical-path monitoring, staged adoption of digital project controls, workforce development and time-bound regulatory approvals. It concludes that sustainable improvement requires shared accountability among clients, contractors, consultants and public regulators.

IIARD INTERNATIONAL JOURNAL OF GEOGRAPHY AND ENVIRONMENTAL MANAGEMENT
Imo State University (NG)
Openalex Percentile: Top 13%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon