Akar Keterlambatan Bongkar Muat akibat Kendala Operasional di Fuel Terminal Camplong

Loading and unloading delays on tankers may arise before berthing or during cargo transfer. This study analyzes the causes, impacts, and dominant factors of operational delays involving MT. Klasogun at Fuel Terminal Camplong. A qualitative descriptive method was applied through observation, interviews, and documentation, followed by Root Cause Analysis (RCA) and a Fishbone diagram. Two groups of constraints were identified. An external factor occurred when a tugboat operated with limited propulsion capability, delaying the berthing process by about two hours. An internal factor occurred when Cargo Oil Pump (COP) No. 2 showed leakage and pressure loss due to a damaged mechanical seal, requiring cargo operations to stop for about four hours while the component was replaced and the system checked. RCA linked the failure to high operating hours, insufficient preventive maintenance, and incomplete pre-operation inspection. Equipment-related problems were the dominant cause. Stronger preventive maintenance, pre-operation checks, tugboat readiness, and ship-terminal coordination are therefore required to reduce delays while maintaining operational safety.

Authors

Publication Details

Published
2026-11-04
DOI
https://doi.org/10.66865/mx431r34
Primary Topic
Maritime Ports and Logistics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Akar Keterlambatan Bongkar Muat akibat Kendala Operasional di Fuel Terminal Camplong

Erwin Sutantyo, Januar Caniago, Marselia
Maritime Ports and Logistics
article

Akar Keterlambatan Bongkar Muat akibat Kendala Operasional di Fuel Terminal Camplong

Erwin Sutantyo, Januar Caniago, Marselia
article en

Abstract

Loading and unloading delays on tankers may arise before berthing or during cargo transfer. This study analyzes the causes, impacts, and dominant factors of operational delays involving MT. Klasogun at Fuel Terminal Camplong. A qualitative descriptive method was applied through observation, interviews, and documentation, followed by Root Cause Analysis (RCA) and a Fishbone diagram. Two groups of constraints were identified. An external factor occurred when a tugboat operated with limited propulsion capability, delaying the berthing process by about two hours. An internal factor occurred when Cargo Oil Pump (COP) No. 2 showed leakage and pressure loss due to a damaged mechanical seal, requiring cargo operations to stop for about four hours while the component was replaced and the system checked. RCA linked the failure to high operating hours, insufficient preventive maintenance, and incomplete pre-operation inspection. Equipment-related problems were the dominant cause. Stronger preventive maintenance, pre-operation checks, tugboat readiness, and ship-terminal coordination are therefore required to reduce delays while maintaining operational safety.

Vol. 1(2)
Openalex Percentile: Top 15%
Maritime Ports and Logistics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon