Excavator-Dump Truck Fleet Planning and Performance Assessment in Road Earthwork: A Case Study

From blasting and excavation to material sourcing, backfilling, haulage planning, and equipment allocation, earthwork strongly influences construction efficiency and project costs. Based on typical engineering parameters, this study establishes a representative road earthwork scenario to define a preliminary construction plan and evaluate the feasibility of the proposed excavator-dump truck combination. Specifically, rock excavation, soil excavation, and backfill shortages are quantified in bank cubic meters (BCM). The required additional soil for haulage is determined by balancing the quantities of material between the excavation and fill areas. The two transport routes are evaluated for safety, with the safer REFO route selected for subsequent analysis. Accordingly, truck payload, transport cycle time, and the required number of trips are determined. The results indicate that approximately 8,337.8 BCM of soil must be transported from Point P. With one Caterpillar 385C FS excavator and 15 CAT 725 trucks, the hauling time is about 23.23 h at 75% efficiency. Thus, it can be found that the selection of routes and operational efficiency have a significant impact on the schedule arrangement and construction planning of the earthwork project.

Authors

Institutions

Publication Details

Journal
Applied and Computational Engineering
Published
2026-11-03
DOI
https://doi.org/10.54254/2755-2721/2026.38491
Primary Topic
Mining Techniques and Economics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Excavator-Dump Truck Fleet Planning and Performance Assessment in Road Earthwork: A Case Study

Zhaohui Qin
Applied and Computational Engineering
Mining Techniques and Economics
article

Excavator-Dump Truck Fleet Planning and Performance Assessment in Road Earthwork: A Case Study

Zhaohui Qin
article en

Abstract

From blasting and excavation to material sourcing, backfilling, haulage planning, and equipment allocation, earthwork strongly influences construction efficiency and project costs. Based on typical engineering parameters, this study establishes a representative road earthwork scenario to define a preliminary construction plan and evaluate the feasibility of the proposed excavator-dump truck combination. Specifically, rock excavation, soil excavation, and backfill shortages are quantified in bank cubic meters (BCM). The required additional soil for haulage is determined by balancing the quantities of material between the excavation and fill areas. The two transport routes are evaluated for safety, with the safer REFO route selected for subsequent analysis. Accordingly, truck payload, transport cycle time, and the required number of trips are determined. The results indicate that approximately 8,337.8 BCM of soil must be transported from Point P. With one Caterpillar 385C FS excavator and 15 CAT 725 trucks, the hauling time is about 23.23 h at 75% efficiency. Thus, it can be found that the selection of routes and operational efficiency have a significant impact on the schedule arrangement and construction planning of the earthwork project.

Applied and Computational EngineeringVol. 278(1)
Suzhou University of Science and Technology (CN)
Openalex Percentile: Top 19%
Mining Techniques and Economics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon