Economic Analysis of Proposed Bosso, Chanchaga and Tagwai Dams Hydroelectric Power Plants

The economic analysis of Bosso, Chanchaga and Tagwai dams proposed storage and off-shore hydroelectric power was conducted. Regression equation was used to estimate the cost of civil engineering work, cost of electromechanical equipments and total cost of establishing the storage and off-shore hydroelectric power plants in each of the dams by summing up the cost of civil engineering work and cost of electromechanical equipments. The result showed that the estimated total cost of establishing Bosso, Chanchaga and Tagwai dams proposed storage hydroelectric power plants were; ₦ 12,205,311,783, ₦ 19, 466,230,000 and ₦ 16, 734, 495, 000 respectively while the estimated total cost of establishing Bosso, Chanchaga and Tagwai off-shore hydroelectric power plants were; ₦ 3, 208, 563,000, ₦ 4,055,384,000 and ₦ 4, 099, 907, 055 respectively

Authors

Institutions

Publication Details

Journal
Nigerian Journal of Physics
Published
2026-11-02
DOI
https://doi.org/10.62292/njp.v35(s).2026.774
Primary Topic
Renewable energy and sustainable power systems
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Economic Analysis of Proposed Bosso, Chanchaga and Tagwai Dams Hydroelectric Power Plants

Aminu Shinkafi Bature, Davidson Odafe Akpootu, Musa Momoh, Abdullahi Yusuf
Nigerian Journal of Physics
Renewable energy and sustainable power systems
article

Economic Analysis of Proposed Bosso, Chanchaga and Tagwai Dams Hydroelectric Power Plants

Aminu Shinkafi Bature, Davidson Odafe Akpootu, Musa Momoh, Abdullahi Yusuf
article en

Abstract

The economic analysis of Bosso, Chanchaga and Tagwai dams proposed storage and off-shore hydroelectric power was conducted. Regression equation was used to estimate the cost of civil engineering work, cost of electromechanical equipments and total cost of establishing the storage and off-shore hydroelectric power plants in each of the dams by summing up the cost of civil engineering work and cost of electromechanical equipments. The result showed that the estimated total cost of establishing Bosso, Chanchaga and Tagwai dams proposed storage hydroelectric power plants were; ₦ 12,205,311,783, ₦ 19, 466,230,000 and ₦ 16, 734, 495, 000 respectively while the estimated total cost of establishing Bosso, Chanchaga and Tagwai off-shore hydroelectric power plants were; ₦ 3, 208, 563,000, ₦ 4,055,384,000 and ₦ 4, 099, 907, 055 respectively

Nigerian Journal of PhysicsVol. 35(S)
Usmanu Danfodiyo University (NG)
Openalex Percentile: Top 36%
Renewable energy and sustainable power systems
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon