Two-Layer HVDC Frequency Coordination with Local Energy Constraints and Planned Support Withdrawal

Finite-energy frequency support through multiple high-voltage direct-current (HVDC) links requires coordination of power delivery, device constraints, and support withdrawal, because maximizing the initial response can exhaust a source too early or deepen the frequency minimum after support ends. This paper develops a two-layer method that separates the energy supplied to a synchronous system by asynchronously connected sources from the power redistributed inside it by embedded links. A local scalar projection enforces the present source and capacitor constraints at every converter, with explicit conditions for discrete invariance, bounded-error sampled execution, finite-rate withdrawal, and the capacitor discharge time. A causal regional linear program allocates support over time and constrains the frequency response after the scheduled withdrawal; its feasibility condition is derived in terms of the remaining source energy, and late calculations or expired instructions revert to local frequency response. In a two-area benchmark with 900 MJ of source energy and a 20 MW internal transfer limit, 5 Hz coordination reduces the maximum frequency depression by 17.38% and 13.83% relative to independently searched static gains, and three-phase average-value electrical realization retains 16.57% and 13.25%. In 70 newly executed plant-perturbation cases with load damping, governor, secondary, inertia, and tie-line parameters varied by up to 20%, the controller improves on fixed droop in every case and on the searched static gains in 63, without device-limit violations; in a three-area extension with three stations the reductions are 6.60% to 17.55% relative to searched static gains and 38.04% to 42.05% relative to fixed droop. Measured calculation times identify the linear program as the only real-time bottleneck and quantify how its size grows with the number of areas and stations.

Authors

Institutions

Publication Details

Journal
Electronics
Published
2026-11-03
DOI
https://doi.org/10.3390/electronics15215096
Primary Topic
Frequency Control in Power Systems
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Two-Layer HVDC Frequency Coordination with Local Energy Constraints and Planned Support Withdrawal

Yuan Si, Shujun Xin, Binqi Ma, Fan Li et al.
Electronics
Frequency Control in Power Systems
article

Two-Layer HVDC Frequency Coordination with Local Energy Constraints and Planned Support Withdrawal

Yuan Si, Shujun Xin, Binqi Ma, Fan Li, Jishuo Qin, Dan Wang
article en

Abstract

Finite-energy frequency support through multiple high-voltage direct-current (HVDC) links requires coordination of power delivery, device constraints, and support withdrawal, because maximizing the initial response can exhaust a source too early or deepen the frequency minimum after support ends. This paper develops a two-layer method that separates the energy supplied to a synchronous system by asynchronously connected sources from the power redistributed inside it by embedded links. A local scalar projection enforces the present source and capacitor constraints at every converter, with explicit conditions for discrete invariance, bounded-error sampled execution, finite-rate withdrawal, and the capacitor discharge time. A causal regional linear program allocates support over time and constrains the frequency response after the scheduled withdrawal; its feasibility condition is derived in terms of the remaining source energy, and late calculations or expired instructions revert to local frequency response. In a two-area benchmark with 900 MJ of source energy and a 20 MW internal transfer limit, 5 Hz coordination reduces the maximum frequency depression by 17.38% and 13.83% relative to independently searched static gains, and three-phase average-value electrical realization retains 16.57% and 13.25%. In 70 newly executed plant-perturbation cases with load damping, governor, secondary, inertia, and tie-line parameters varied by up to 20%, the controller improves on fixed droop in every case and on the searched static gains in 63, without device-limit violations; in a three-area extension with three stations the reductions are 6.60% to 17.55% relative to searched static gains and 38.04% to 42.05% relative to fixed droop. Measured calculation times identify the linear program as the only real-time bottleneck and quantify how its size grows with the number of areas and stations.

ElectronicsVol. 15(21)
North China Electric Power University (CN), State Grid Corporation of China (China) (CN)
Openalex Percentile: Top 26%
Frequency Control in Power Systems
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon