Financial Monitoring and Financial Overruns: A Case of the Kigali Infrastructure Project (KIP) in Nyarugenge District, Rwanda

Financial overruns threaten the timely and efficient delivery of urban infrastructure, yet the relative contribution of different monitoring practices remains insufficiently documented in specific Rwandan projects. This study examined the associations of budget monitoring, cash-flow monitoring and cost-control monitoring with perceived financial-overrun control in the Kigali Infrastructure Project, Nyarugenge District. A descriptive mixed-methods design was used. Of 214 questionnaires administered, 204 were returned (95.3%); three project managers also participated in key-informant interviews. Questionnaire data were analysed using descriptive statistics, Pearson correlations and multiple regression in SPSS version 23, while interviews were analysed thematically and yielded four themes that broadly echoed the survey results. The regression model accounted for 77.3% of variation in the study’s financial-overrun outcome (R² = .773; F(3, 200) = 226.725, p < .001). Budget monitoring (β = .626, p < .001) and cost-control monitoring (β = .379, p < .001) were significant positive predictors; cash-flow monitoring was not (β = .012, p = .850) after adjustment for the other predictors. The findings identify budget oversight and expenditure control as the strongest correlates of respondents’ reported success in containing overruns. Project managers should strengthen variance review, corrective-action tracking and cost-control procedures while investigating operational barriers to cash-flow effectiveness. Because the evidence is cross-sectional and based principally on stakeholder reports, it cannot establish causation or independently verify actual changes in project costs. Keywords: Budget Monitoring, Cash-Flow Monitoring, Cost Control, Financial Overruns, Infrastructure Projects

Authors

Institutions

Publication Details

Journal
Journal of Entrepreneurship & Project Management
Published
2026-11-02
DOI
https://doi.org/10.53819/81018102t3196
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Financial Monitoring and Financial Overruns: A Case of the Kigali Infrastructure Project (KIP) in Nyarugenge District, Rwanda

Gitahi Njenga, Irene Umuhoza
Journal of Entrepreneurship & Project Management
Construction Project Management and Performance
article

Financial Monitoring and Financial Overruns: A Case of the Kigali Infrastructure Project (KIP) in Nyarugenge District, Rwanda

Gitahi Njenga, Irene Umuhoza
article en

Abstract

Financial overruns threaten the timely and efficient delivery of urban infrastructure, yet the relative contribution of different monitoring practices remains insufficiently documented in specific Rwandan projects. This study examined the associations of budget monitoring, cash-flow monitoring and cost-control monitoring with perceived financial-overrun control in the Kigali Infrastructure Project, Nyarugenge District. A descriptive mixed-methods design was used. Of 214 questionnaires administered, 204 were returned (95.3%); three project managers also participated in key-informant interviews. Questionnaire data were analysed using descriptive statistics, Pearson correlations and multiple regression in SPSS version 23, while interviews were analysed thematically and yielded four themes that broadly echoed the survey results. The regression model accounted for 77.3% of variation in the study’s financial-overrun outcome (R² = .773; F(3, 200) = 226.725, p < .001). Budget monitoring (β = .626, p < .001) and cost-control monitoring (β = .379, p < .001) were significant positive predictors; cash-flow monitoring was not (β = .012, p = .850) after adjustment for the other predictors. The findings identify budget oversight and expenditure control as the strongest correlates of respondents’ reported success in containing overruns. Project managers should strengthen variance review, corrective-action tracking and cost-control procedures while investigating operational barriers to cash-flow effectiveness. Because the evidence is cross-sectional and based principally on stakeholder reports, it cannot establish causation or independently verify actual changes in project costs. Keywords: Budget Monitoring, Cash-Flow Monitoring, Cost Control, Financial Overruns, Infrastructure Projects

Journal of Entrepreneurship & Project ManagementVol. 10(6)
Mount Kigali University (RW)
Industry, innovation and infrastructure, Sustainable cities and communities
Openalex Percentile: Top 13%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon
Financial Monitoring and Financial Overruns: A Case of the Kigali Infrastructure Project (KIP) in Nyarugenge District, Rwanda — Gitahi Njenga, Irene Umuhoza · Journal of Entrepreneurship & Project Management (2026) | TGRS Research Map | TGRS