ANALISIS IMPLEMENTASI OVER LOAD SHEDDING (OLS) PADA SUTT 150 KV JAYAKERTAS-KERTOSONO SEBAGAI LANGKAH OPTIMASI KEANDALAN SUBSISTEM KEDIRI 1,2 DI WILAYAH UP2B JAWA TIMUR

The reliability of power transmission systems is essential for maintaining electricity supply continuity, particularly under contingency conditions that may cause transmission line overloading. This study analyzes the implementation of Over Load Shedding (OLS) on the 150 kV Jayakertas–Kertosono Transmission Line to improve the reliability of the Kediri 1,2 subsystems. The analysis uses actual peak load data from May 2026 and projected peak load data for 2026 under an N-1 contingency scenario. Without OLS, the contingency caused transmission line loading to exceed its nominal capacity and Over Current Relay (OCR) setting, potentially resulting in circuit breaker tripping and widespread outages, with an interrupted load of 422,61 MW. With OLS implementation, Stage-1 successfully shed 53,89 MW under actual peak load conditions, reducing line loading to 96,85%. Under the 2026 projected peak load scenario, Stage-1 Overload Shedding (OLS) shed 57.10 MW of load, although the final transmission line loading remained at 103.12% of its nominal thermal capacity. This indicates that Stage-1 OLS did not fully resolve the overload condition; therefore, corrective actions by the system operator and the activation of subsequent OLS stages may be required, depending on the prevailing system conditions and protection coordination. Assuming a fault duration of one hour, OLS implementation under the 2026 projected scenario reduced the Energy Not Served (ENS) by 365,510 kWh or approximately 86.5%, and reduced potential economic losses by approximately IDR 528 million. The results demonstrate that OLS effectively mitigates the impact of N-1 contingencies on supply continuity and potential economic losses, although further corrective measures are necessary to ensure that transmission line loading returns to within the permissible operating limits. ABSTRAK Keandalan sistem transmisi tenaga listrik sangat penting untuk menjaga kontinuitas pasokan listrik, khususnya dalam kondisi kontingensi yang dapat menyebabkan pembebanan berlebih pada saluran transmisi. Penelitian ini menganalisis penerapan Over Load Shedding (OLS) pada Saluran Transmisi 150 kV Jayakertas–Kertosono sebagai upaya meningkatkan keandalan subsistem Kediri 1,2. Analisis dilakukan menggunakan data beban puncak aktual bulan Mei 2026 dan proyeksi beban puncak tahun 2026 dalam kondisi kontingensi N-1. Tanpa penerapan OLS, kondisi kontingensi menyebabkan pembebanan saluran transmisi melebihi kapasitas nominal dan setting Over Current Relay (OCR), sehingga berpotensi menyebabkan pelepasan circuit breaker dan gangguan pasokan listrik secara meluas dengan beban padam sebesar 422,61 MW. Setelah penerapan OLS, Tahap-1 berhasil melepaskan beban sebesar 53,89 MW pada kondisi beban puncak aktual, sehingga pembebanan saluran turun menjadi 96,85%. Pada kondisi proyeksi beban puncak tahun 2026, OLS Tahap-1 melepaskan beban sebesar 57,10 MW meskipun tingkat pembebanan akhirnya masih mencapai 103,12% dari kapasitas termal nominal. Kondisi tersebut menunjukkan bahwa OLS Tahap-1 belum sepenuhnya mengatasi pembebanan berlebih, sehingga diperlukan tindakan korektif operator dan aktivasi tahapan OLS selanjutnya sesuai kondisi sistem dan koordinasi proteksi. Berdasarkan asumsi durasi gangguan satu jam, penerapan OLS pada skenario proyeksi tahun 2026 mengurangi Energy Not Served (ENS) sebesar 365.510 kWh atau sekitar 86,5%, serta menurunkan potensi kerugian ekonomi sekitar Rp528 juta. Hasil penelitian menunjukkan bahwa OLS efektif mengurangi dampak kontingensi N-1 terhadap kontinuitas pasokan listrik dan potensi kerugian ekonomi meskipun pengendalian lanjutan masih diperlukan untuk memastikan pembebanan memenuhi batas operasi yang diizinkan. Kata Kunci: Over Load Shedding (OLS), Saluran Transmisi 150 kV, kontingensi N-1, keandalan sistem, Energy Not Served (ENS

Authors

Institutions

Publication Details

Journal
eLEKTRIKA
Published
2026-10-30
DOI
https://doi.org/10.26623/elektrika.v18i2.15917
Primary Topic
Thermal Analysis in Power Transmission
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS IMPLEMENTASI OVER LOAD SHEDDING (OLS) PADA SUTT 150 KV JAYAKERTAS-KERTOSONO SEBAGAI LANGKAH OPTIMASI KEANDALAN SUBSISTEM KEDIRI 1,2 DI WILAYAH UP2B JAWA TIMUR

Ida Widihastuti, Rendy Nur Hidayatullah
eLEKTRIKA
Thermal Analysis in Power Transmission
article

ANALISIS IMPLEMENTASI OVER LOAD SHEDDING (OLS) PADA SUTT 150 KV JAYAKERTAS-KERTOSONO SEBAGAI LANGKAH OPTIMASI KEANDALAN SUBSISTEM KEDIRI 1,2 DI WILAYAH UP2B JAWA TIMUR

Ida Widihastuti, Rendy Nur Hidayatullah
article en

Abstract

The reliability of power transmission systems is essential for maintaining electricity supply continuity, particularly under contingency conditions that may cause transmission line overloading. This study analyzes the implementation of Over Load Shedding (OLS) on the 150 kV Jayakertas–Kertosono Transmission Line to improve the reliability of the Kediri 1,2 subsystems. The analysis uses actual peak load data from May 2026 and projected peak load data for 2026 under an N-1 contingency scenario. Without OLS, the contingency caused transmission line loading to exceed its nominal capacity and Over Current Relay (OCR) setting, potentially resulting in circuit breaker tripping and widespread outages, with an interrupted load of 422,61 MW. With OLS implementation, Stage-1 successfully shed 53,89 MW under actual peak load conditions, reducing line loading to 96,85%. Under the 2026 projected peak load scenario, Stage-1 Overload Shedding (OLS) shed 57.10 MW of load, although the final transmission line loading remained at 103.12% of its nominal thermal capacity. This indicates that Stage-1 OLS did not fully resolve the overload condition; therefore, corrective actions by the system operator and the activation of subsequent OLS stages may be required, depending on the prevailing system conditions and protection coordination. Assuming a fault duration of one hour, OLS implementation under the 2026 projected scenario reduced the Energy Not Served (ENS) by 365,510 kWh or approximately 86.5%, and reduced potential economic losses by approximately IDR 528 million. The results demonstrate that OLS effectively mitigates the impact of N-1 contingencies on supply continuity and potential economic losses, although further corrective measures are necessary to ensure that transmission line loading returns to within the permissible operating limits. ABSTRAK Keandalan sistem transmisi tenaga listrik sangat penting untuk menjaga kontinuitas pasokan listrik, khususnya dalam kondisi kontingensi yang dapat menyebabkan pembebanan berlebih pada saluran transmisi. Penelitian ini menganalisis penerapan Over Load Shedding (OLS) pada Saluran Transmisi 150 kV Jayakertas–Kertosono sebagai upaya meningkatkan keandalan subsistem Kediri 1,2. Analisis dilakukan menggunakan data beban puncak aktual bulan Mei 2026 dan proyeksi beban puncak tahun 2026 dalam kondisi kontingensi N-1. Tanpa penerapan OLS, kondisi kontingensi menyebabkan pembebanan saluran transmisi melebihi kapasitas nominal dan setting Over Current Relay (OCR), sehingga berpotensi menyebabkan pelepasan circuit breaker dan gangguan pasokan listrik secara meluas dengan beban padam sebesar 422,61 MW. Setelah penerapan OLS, Tahap-1 berhasil melepaskan beban sebesar 53,89 MW pada kondisi beban puncak aktual, sehingga pembebanan saluran turun menjadi 96,85%. Pada kondisi proyeksi beban puncak tahun 2026, OLS Tahap-1 melepaskan beban sebesar 57,10 MW meskipun tingkat pembebanan akhirnya masih mencapai 103,12% dari kapasitas termal nominal. Kondisi tersebut menunjukkan bahwa OLS Tahap-1 belum sepenuhnya mengatasi pembebanan berlebih, sehingga diperlukan tindakan korektif operator dan aktivasi tahapan OLS selanjutnya sesuai kondisi sistem dan koordinasi proteksi. Berdasarkan asumsi durasi gangguan satu jam, penerapan OLS pada skenario proyeksi tahun 2026 mengurangi Energy Not Served (ENS) sebesar 365.510 kWh atau sekitar 86,5%, serta menurunkan potensi kerugian ekonomi sekitar Rp528 juta. Hasil penelitian menunjukkan bahwa OLS efektif mengurangi dampak kontingensi N-1 terhadap kontinuitas pasokan listrik dan potensi kerugian ekonomi meskipun pengendalian lanjutan masih diperlukan untuk memastikan pembebanan memenuhi batas operasi yang diizinkan. Kata Kunci: Over Load Shedding (OLS), Saluran Transmisi 150 kV, kontingensi N-1, keandalan sistem, Energy Not Served (ENS

eLEKTRIKAVol. 18(2)
Sultan Agung Islamic University (ID)
Openalex Percentile: Top 17%
Thermal Analysis in Power Transmission
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon