Monitoring and Control as Success Tools in Factory Construction: An Earned Value Analysis

Factory construction projects involve high investment, tight schedules, and multiple stakeholders, making monitoring and control decisive processes for project success. This paper analyses, through a practical case, the application of Earned Value Management (EVM) as an integrated schedule and cost control tool in the construction of an agro-industrial processing plant in northern Mozambique. The applied, quantitative study is grounded in a literature review and a single exploratory case study using simulated monthly Planned Value, Earned Value, and Actual Cost data, parameterized on documented deviation drivers (rainy-season productivity loss, delays in imported inputs, and price escalation) to protect site confidentiality. The data-collection instrument was a structured monthly project-monitoring record with explicit physical-progress rules (quantities completed and weighted milestones); the sample corresponds to six consecutive monthly reporting cycles (months 1 to 6) of a single agro-industrial processing-plant construction project in Ribaué, Nampula province, selected purposively as a case rather than drawn from a probabilistic population. Results show a mean Schedule Performance Index (SPI) of 0.88 (SD = 0.015) and a mean Cost Performance Index (CPI) of 0.91 (SD = 0.024) across the six months, with the CPI declining monotonically from 0.95 to 0.88 and crossing the critical 0.90 threshold in month five; by month six, SPI stood at 0.89 and CPI at 0.88, indicating simultaneous schedule slippage and cost overrun, with an estimate at completion (EAC) of about 13.66 million MZN, roughly 14% above the 12.0 million MZN budget (scenario range +7% to +21%). A work-package breakdown shows that earthworks and foundations concentrate half of the cost overrun, while steel structure and roofing concentrate 71% of the schedule slippage. The study concludes that EVM, framed within the PMBOK monitoring and controlling process group, enables early deviation detection and diagnosis and supports timely corrective decisions, confirming its relevance as a success tool in industrial construction; because the data are simulated, the results demonstrate the method rather than measure real performance.

Authors

Institutions

Publication Details

Journal
International Multidisciplinary Journal of Emerging Technologies and Applications
Published
2026-10-31
DOI
https://doi.org/10.67294/h5qg2t42
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Monitoring and Control as Success Tools in Factory Construction: An Earned Value Analysis

Chibalonza Mpenda, Sergio Vicente Gabriel
International Multidisciplinary Journal of Emerging Technologies and Applications
Construction Project Management and Performance
article

Monitoring and Control as Success Tools in Factory Construction: An Earned Value Analysis

Chibalonza Mpenda, Sergio Vicente Gabriel
article en

Abstract

Factory construction projects involve high investment, tight schedules, and multiple stakeholders, making monitoring and control decisive processes for project success. This paper analyses, through a practical case, the application of Earned Value Management (EVM) as an integrated schedule and cost control tool in the construction of an agro-industrial processing plant in northern Mozambique. The applied, quantitative study is grounded in a literature review and a single exploratory case study using simulated monthly Planned Value, Earned Value, and Actual Cost data, parameterized on documented deviation drivers (rainy-season productivity loss, delays in imported inputs, and price escalation) to protect site confidentiality. The data-collection instrument was a structured monthly project-monitoring record with explicit physical-progress rules (quantities completed and weighted milestones); the sample corresponds to six consecutive monthly reporting cycles (months 1 to 6) of a single agro-industrial processing-plant construction project in Ribaué, Nampula province, selected purposively as a case rather than drawn from a probabilistic population. Results show a mean Schedule Performance Index (SPI) of 0.88 (SD = 0.015) and a mean Cost Performance Index (CPI) of 0.91 (SD = 0.024) across the six months, with the CPI declining monotonically from 0.95 to 0.88 and crossing the critical 0.90 threshold in month five; by month six, SPI stood at 0.89 and CPI at 0.88, indicating simultaneous schedule slippage and cost overrun, with an estimate at completion (EAC) of about 13.66 million MZN, roughly 14% above the 12.0 million MZN budget (scenario range +7% to +21%). A work-package breakdown shows that earthworks and foundations concentrate half of the cost overrun, while steel structure and roofing concentrate 71% of the schedule slippage. The study concludes that EVM, framed within the PMBOK monitoring and controlling process group, enables early deviation detection and diagnosis and supports timely corrective decisions, confirming its relevance as a success tool in industrial construction; because the data are simulated, the results demonstrate the method rather than measure real performance.

International Multidisciplinary Journal of Emerging Technologies and ApplicationsVol. 1(7)
Universidad Internacional Iberoamericana (PR), Universidad Internacional Iberoamericana (MX)
Openalex Percentile: Top 10%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon