Analysis of Impact, Causes, and Mitigation of Contract Change Orders (CCOs) in Transmission Line and Substation Projects

Contract Change Orders (CCOs) remain a major issue in power infrastructure projects because they can affect both contract schedule and contract value. However, empirical studies examining CCOs specifically in high-voltage transmission line and substation projects remain limited. This study analyzes the impact, causes, and mitigation of CCOs in 150 kV transmission line and substation projects using a mixed-method approach. We conducted a quantitative analysis of historical data from 62 projects implemented in South, East, and North Kalimantan between 2017 and 2025, including Extension Substation, New Substation, and Transmission Line projects. We used descriptive statistics, Shapiro–Wilk tests, Kruskal–Wallis tests, and Dunn’s post-hoc tests to compare variations in schedule and contract value across project categories. We obtained qualitative data through semi-structured interviews with owners, engineering consultants, contractors, supervision consultants, and operation units. The results indicate that Transmission Line projects have significantly more variation in schedule and contract value than substation projects, particularly Extension Substation projects. Design and consultant issues, uncertainties about site conditions, gaps in stakeholder coordination, owner-initiated changes, regulatory and governance issues, land acquisition and right-of-way issues, and external factors are the main causes of CCOs. The results also show that land acquisition and right-of-way issues are a dominant project-specific driver for Transmission Line projects and often result in route adjustments, design revisions, quantity changes, and schedule extensions. This research contributes to change order management by providing sector-specific evidence for power infrastructure projects. It highlights the importance of early design maturity, site verification, stakeholder coordination, and land and ROW readiness in mitigating avoidable CCOs.

Authors

Institutions

Publication Details

Journal
Rekayasa Sipil
Published
2026-10-30
DOI
https://doi.org/10.21776/ub.rekayasasipil.2026.020.03.12
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Impact, Causes, and Mitigation of Contract Change Orders (CCOs) in Transmission Line and Substation Projects

Arief Setiawan Budi Nugroho, Tantri Nastiti Handayani, Samuel Starry Yanuar
1 links
Rekayasa Sipil
Construction Project Management and Performance
article

Analysis of Impact, Causes, and Mitigation of Contract Change Orders (CCOs) in Transmission Line and Substation Projects

Arief Setiawan Budi Nugroho, Tantri Nastiti Handayani, Samuel Starry Yanuar
article en

Abstract

Contract Change Orders (CCOs) remain a major issue in power infrastructure projects because they can affect both contract schedule and contract value. However, empirical studies examining CCOs specifically in high-voltage transmission line and substation projects remain limited. This study analyzes the impact, causes, and mitigation of CCOs in 150 kV transmission line and substation projects using a mixed-method approach. We conducted a quantitative analysis of historical data from 62 projects implemented in South, East, and North Kalimantan between 2017 and 2025, including Extension Substation, New Substation, and Transmission Line projects. We used descriptive statistics, Shapiro–Wilk tests, Kruskal–Wallis tests, and Dunn’s post-hoc tests to compare variations in schedule and contract value across project categories. We obtained qualitative data through semi-structured interviews with owners, engineering consultants, contractors, supervision consultants, and operation units. The results indicate that Transmission Line projects have significantly more variation in schedule and contract value than substation projects, particularly Extension Substation projects. Design and consultant issues, uncertainties about site conditions, gaps in stakeholder coordination, owner-initiated changes, regulatory and governance issues, land acquisition and right-of-way issues, and external factors are the main causes of CCOs. The results also show that land acquisition and right-of-way issues are a dominant project-specific driver for Transmission Line projects and often result in route adjustments, design revisions, quantity changes, and schedule extensions. This research contributes to change order management by providing sector-specific evidence for power infrastructure projects. It highlights the importance of early design maturity, site verification, stakeholder coordination, and land and ROW readiness in mitigating avoidable CCOs.

Rekayasa SipilVol. 20(3)
Universitas Gadjah Mada (ID)
Industry, innovation and infrastructure, Climate action
Openalex Percentile: Top 10%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon
Analysis of Impact, Causes, and Mitigation of Contract Change Orders (CCOs) in Transmission Line and Substation Projects — Arief Setiawan Budi Nugroho, Tantri Nastiti Handayani, et al. · Rekayasa Sipil (2026) | TGRS Research Map | TGRS