Topologically adaptive ant colony optimization for scheduling mega-structure pile foundations with endogenous spatio-temporal constraints

Pile foundation scheduling of super-large engineering structure presents significant concerns and challenges due to the dynamically triggered and evolved vibration exclusion zones generated by impact boring. However, conventional re­source-constrained project scheduling theories often exhibit spatial blindness, resulting in cascading construction critical path delays. Therefore, this study proposes a Topologically Adaptive Ant Colony Optimization (TA-ACO) algorithm embedded within a state-dependent simulation environment. The algorithm employs a dual-colony cooperative mechanism to effectively de­couple the adversarial resource coupling between piling crews and grouting crews. Specifically, a novel look-ahead heuristic strategy is introduced, guiding crews to maximize spatial sparsity, which is analogous to solving the Maximum Independent Set problem and avoiding topological deadlocks. Computational experiments demonstrate that TA-ACO effectively mitigates spatial fragmentation and reduces the project makespan by 21.5% to 28.3% across different large-scale instances, compared to the industry-standard greedy strategy. The engineering application results of large airports show that the proposed algo­rithm compressed the construction period of a critical zone, which includes 97 pile foundations, from 47 days to 34 days, se­curing a valuable 13-day lead time for subsequent superstructure assembly.

Authors

Institutions

Publication Details

Journal
Journal of Civil Engineering and Management
Published
2026-10-29
DOI
https://doi.org/10.3846/jcem.2026.28639
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Topologically adaptive ant colony optimization for scheduling mega-structure pile foundations with endogenous spatio-temporal constraints

Qiaoling Min, Jingbo Hao, Renchao Wang, Libin Han et al.
Journal of Civil Engineering and Management
Resource-Constrained Project Scheduling
article

Topologically adaptive ant colony optimization for scheduling mega-structure pile foundations with endogenous spatio-temporal constraints

Qiaoling Min, Jingbo Hao, Renchao Wang, Libin Han, Mingchao Li, Mengxi Zhang, Xuesong Xiang
article en

Abstract

Pile foundation scheduling of super-large engineering structure presents significant concerns and challenges due to the dynamically triggered and evolved vibration exclusion zones generated by impact boring. However, conventional re­source-constrained project scheduling theories often exhibit spatial blindness, resulting in cascading construction critical path delays. Therefore, this study proposes a Topologically Adaptive Ant Colony Optimization (TA-ACO) algorithm embedded within a state-dependent simulation environment. The algorithm employs a dual-colony cooperative mechanism to effectively de­couple the adversarial resource coupling between piling crews and grouting crews. Specifically, a novel look-ahead heuristic strategy is introduced, guiding crews to maximize spatial sparsity, which is analogous to solving the Maximum Independent Set problem and avoiding topological deadlocks. Computational experiments demonstrate that TA-ACO effectively mitigates spatial fragmentation and reduces the project makespan by 21.5% to 28.3% across different large-scale instances, compared to the industry-standard greedy strategy. The engineering application results of large airports show that the proposed algo­rithm compressed the construction period of a critical zone, which includes 97 pile foundations, from 47 days to 34 days, se­curing a valuable 13-day lead time for subsequent superstructure assembly.

Journal of Civil Engineering and ManagementVol. 32(7)
Tianjin University (CN), Xinjiang University of Technology (CN)
National Natural Science Foundation of China, Tianjin Science and Technology Program
Industry, innovation and infrastructure, Sustainable cities and communities
Openalex Percentile: Top 10%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon
Topologically adaptive ant colony optimization for scheduling mega-structure pile foundations with endogenous spatio-temporal constraints — Qiaoling Min, Jingbo Hao, et al. · Journal of Civil Engineering and Management (2026) | TGRS Research Map | TGRS